IRS Logo
Print

Construction Industry Audit Technique Guide (ATG) - Chapter 6

Publication Date - May 2009

NOTE: This document is not an official pronouncement of the law or the position of the Service and can not be used, cited, or relied upon as such. This guide is current through the publication date. Since changes may have occurred after the publication date that would affect the accuracy of this document, no guarantees are made concerning the technical accuracy after the publication date.


Table of Contents
Chapter 5 / Chapter 7


Chapter 6: Financial Accounting Versus Tax Accounting

Introduction

The accounting methods available within in the construction industry are unique to this industry. Understanding both the financial accounting and tax accounting requirements is important, so the proper book-to-tax adjustments are made.

Financial Accounting

The primary sources for generally accepted accounting principles (GAAP) for accounting for construction contracts are Accounting Research Bulletin (ARB) No. 45, Long-Term, Construction-Type Contracts and Statement of Position (SOP) 81-1, Accounting for Performance of Construction-Type and Certain Production-Type Contracts. Under (GAAP) there are two methods of recognizing revenues on construction contracts.

ARB 45, which was issued in 1955, describes the two generally accepted methods of accounting for long-term construction type contracts; the percentage of completion method and the completed contract method. Because of the complexities and uncertainties in accounting for contracts, SOP 81-1 was issued in 1981 to provide additional guidance on the application of generally accepted accounting principles (GAAP).

Under SOP 81-1, the two methods are not alternatives from which a contractor is free to choose. SOP 81-1 establishes a strong preference for the percentage of completion method on the presumption that contractors have the ability to make estimates that are sufficiently dependable.

Therefore, the financial statements (whether audited, reviewed, or complied) that are prepared for bonding, banking, or other reporting purposes are almost exclusively prepared using the percentage of completion accounting method. However, in some circumstances, where the estimation of the final outcome may be impractical except to assure no loss will be incurred, the percentage of completion method will use a zero profit method (i.e. equal amount of revenue and cost are recognized until the results can be more precisely estimated).

The completed contract method may be used for financial purposes in circumstances in which the financial position would not vary materially from the percentage of completion method (i.e. this would primarily occur with shot-term contracts). Additionally, the completed contract method may be used in circumstances in which the contractor cannot make reasonable estimates.

However, as discussed in the chapter on Small Contractors and Large Contractors, many more accounting method choices are available to the contractor for tax purposes, depending on the length of the contract, the type of construction involved, and the average annual gross receipts of the taxpayer.

International Accounting Standards

Similar to SOP 81-1, which is a United States standard, International Accounting Standard (IAS) 11 provides guidance for the accounting of the revenues and costs of construction contracts. Under IAS 11, the percentage of completion method should be used when the outcome of a construction contract can be reasonably estimated. In circumstances in which the outcome cannot be reasonably estimated, no profit should be recognized. Contract revenue should only be recognized to the extent of contract costs are incurred.

Balance Sheet Accounts

When accounting for contracts using the percentage of completion method (PCM), costs determine the revenue and not the contract’s earned or billed income, recognition. Determining completion by costs (Total Costs Incurred divided by Total Estimated Costs) is a computation not made through the day-to-day book recording procedures. For instance, there is not a general ledger account for total estimated contract costs.

To account for the difference between percentage of completion method and billings, two balance sheet accounts are created:

  1. Costs and Estimated Earnings in Excess of Billings (Asset)
  2. Billings in Excess of Costs and Estimated Earnings (Liability)
Example:

This situation illustrates the concept of journal entries for a construction contract using the percentage of completion method. The contractor entered into a long-term construction contract during the 2001 taxable year. The total estimated contract price is $3,000,000, the total estimated contract costs are $2,000,000 and the contract is to be completed in 2002. The total costs incurred on this contract during 2001 are $1,000,000. The contractor billed the customer $1,200,000 during 2001.

During the tax year journal entries to record the transactions of this contract would be recorded as shown below. (Note: the two entries below are a summary of the numerous transactions that would have been recorded as the costs and billings were incurred.

Journal Entries Using Percentage of Completion Method
Journal Entries Debit Credit
Costs Incurred

$1,000,000

 

Accounts Payable

 

$1,000,000

Accounts Receivable

$1,200,000

 

Costs and Estimated Earnings in Excess of Billings

 

$1,200,000

At year-end, the contractor would determine the income to be included under the percentage of completion method as follows:

Year-End Percentage of Completion Method

Total Costs Incurred ($1,000,000)
Divided By
Total Estimated Costs ($2,000,000)

Times

Estimated Contract Price ($3,000,000)

Equals

PCM Income ($1,500,000)

The necessary to bring the books and financial statements in accordance with the percentage of completion method would be as follows:

Adjusting Journal Entry for Percentage of Completion Method
Journal Entries Debit Credit
Costs and Estimated Earnings in Excess of Billings

$1,500,000

 

Income

 

$1,500,000

At year-end the costs and estimated earnings in excess of billings account has a debit balance of $300,000 and thus is represent as an asset on the balance sheet.

Basically, these two balance sheet accounts represent the difference between the accrual method and the percentage-of-completion method for reporting income on a long-term contract. Under either method, the costs related to the long-term contract are deducted as incurred. Therefore, generally no difference exists between the two

methods for costs.

Accrual vs. Percentage of Completion Methods
Accrual vs. Percentage of Completion Methods Amount

Income Billings per Accrual Method

$1,200,000

Income per Percentage of Completion Method

$1,500,000

Costs and Earnings in Excess of Billings

$300,000

Balance Sheet Reporting

A basic reporting principle prevents assets and liabilities from being netted or offset against each other. Thus both accounts (Costs and Earnings in Excess of Billings and Earnings and Costs in Excess of billings) should be present on the balance sheet. The following procedures are performed at year-end:

  1. For each contract in progress at year-end, the total cost incurred to date plus the estimated earnings (on percentage of completion method) is reduced by the total amount of bills rendered to arrive at a net balance. The net balance, for each contract, will be a debit if the total costs and estimated earnings exceed the billings and a credit if the billings exceed the costs and estimated earnings.
  2. All contracts that have a debit balance are added together with the total shown as an asset on the balance sheet.
  3. All contracts that have a credit balance are added together with the total shown as a liability on the balance sheet.

See the Contracts In Process Schedule at the end of the chapter for an illustration of the procedures above.

Book and Tax Differences

Schedule M-1 and M-3 adjustments result from both timing differences and permanent differences between financial and tax accounting. The following items are intended to point out some of the differences in financial and tax accounting that is unique to the construction industry. These differences should be reconciled through Schedule M-1 and M-3 adjustments.

Revenue Recognition

As discussed above, Statement of Position 81-1 (SOP 81-1) virtually requires construction companies to report income on the percentage of completion method. Generally, the bonding company or a lending bank will require the taxpayer to submit audited (possibly reviewed) financial statements, which will be reported on the percentage of completion method. For tax accounting, the contractor may use a different method, such as completed contract method, percentage of completion method, or capitalized cost method.

Contract Related Services

SOP 81-1 paragraph 12 provides a listing of contracts that are covered by this statement. Included in that listing are engineers, architects, and construction management taxpayers. Therefore, for financial purposes these contracts would be accounted for under the percentage of completion method. However, for tax purposes, they generally cannot use a long-term contract method (e.g., completed contract or percentage of completion). Revenue Ruling 70-67, Revenue Ruling 80-18, Revenue Ruling 82-134, Revenue Ruling 84-32.

Determining Completion for Percentage of Completion Method

SOP 81-1 paragraph 44 provides a number of methods to measure the extent of progress towards completion. They include the cost-to-cost method, variations of the cost-to-cost method, efforts expended method, the units-of-delivery method, and the units-of-work-performed method. For tax purposes, IRC § 460 generally requires the cost-to-cost method. However, the taxpayer may also elect the percentage of completion, 10% method in which none of the contract revenue or costs is included in taxable income until the contract is 10% complete. The contractor may also elect the simplified cost-to-cost method to determine contract completion.

Loss Recognition

SOP 81-1 paragraph 85 requires the contractor to report the total loss on a contract as soon as it is evident that a loss will occur. “When the current estimates of total contract revenue and contract cost indicate a loss, a provision for the entire loss on the contract should be made. Provisions for losses should be made in the period in which they become evident under either the percentage-of-completion method or the completed-contract method.” However, for tax purposes, the loss is not recognized until the job is completed, if on the completed contract method, and as incurred, if on the percentage of completion method.

Sample Financial Statements using Percentage of Completion Method

The exhibits below illustrate the financial statements when reporting construction contracts on the percentage of completion method. They also include items to consider when reviewing these statements.

  • Exhibit 6A - Balance Sheet
  • Exhibit 6B - Statement of Income and Retained Earnings
  • Exhibit 6C - Schedule 1 – Earnings from Contracts
  • Exhibit 6D - Schedule 2 – Contracts Completed
  • Exhibit 6E - Schedule 3 – Contracts in Progress

Exhibit 6A XYZ Corporation Balance Sheet December 31, 2002
Assets: Current Assets: Cash

$9,000

 

Contract Receivables

$335,000

 

Costs & Estimated Earnings in Excess of Billings 1

$28,711

 

Total Current Assets

$372,711

$372,711

Property & Equipment:

 

 

Furniture, Fixtures, & Equipment

$6,000

 

Accumulated Depreciation

($1,500)

 

Total Property and Equipment

$4,500

$4,500

Other Assets: Deposits

$750

 

Total Other Assets

$750

$750

Total Assets

 

$377,961

Liabilities and Stockholder's Equity: Liabilities: Accounts Payable

$121,000

 

Accrued Liabilities

$17,000

 

Deferred Income Taxes

$36,000

 

Billings in Excess of Costs and Estimated Earnings1

$5,666

 

Total Liabilities

$179,666

$179,666

Stockholder’s Equity: Common Stock

$1,000

 

Retained Earnings

$197,295

 

Total Stockholder’s Equity

$198,295

$198,295

Total Liabilities and Stockholder’s Equity

 

$377,961

Notes

1 This account should reconcile to the Schedule 3 – Contracts in Progress

Exhibit 6B XYZ Corporation Statement of Income and Retained Earnings December 31, 2002
Contract Revenue Earned 1

$1,439,159

Less Costs of Revenue Earned 1

($1,174,000)

Gross Profit

$265,159

Less General and Administrative Expenses

($199,000)

Income before Income Taxes

$66,159

Less Income Taxes:  
Current Income Taxes

($12,000)

Deferred Income Taxes

($4,000)

Net Income 2

$50,159

Add Beginning Retained Earnings

$147,136

Ending Retained Earnings

$197,295

Exhibit 6C XYZ Corporation Schedule 1 – Earnings from Contracts Year Ended December 31, 2002
Description Revenues Earned Cost of Revenues Gross Profit (Loss)
Contracts Completed during the Year1

$502,000

$361,000

$141,000

Plus Contracts in Progress at Year-End2

$937,159

$813,000

$124,159

Earnings from Contracts

$1,439,159

$1,174,000

$265,159

Notes

1 This amount is from Schedule 2 - Contracts Completed. It represents the amounts of revenue earned and costs incurred during the 2002 tax year.

2 This amount is from Schedule 3 – Contracts in Progress. It represents the amounts of revenue earned and costs incurred during the 2002 tax year.

Exhibit 6D XYZ Corporation Schedule 2 – Contracts Completed Year Ended December 31, 2002
Project Number Construction Project Revenues Earned 1 Cost Of Revenues 1 Gross Profit (Loss) 1 Revenues Earned 2 Cost Of Revenues 2 Gross Profit (Loss) 2 Revenues Earned 3 Cost Of Revenues 3 Gross Profit (Loss) 3

121

John’s Store

$312,000

$248,000

$64,000

$193,000

$172,000

$21,000

$119,000

$76,000

$43,000

122

Ron’s Club

$267,000

$197,000

$70,000

$178,000

$144,000

$34,000

$89,000

$53,000

$36,000

127

Parking Lot

$403,000

$312,000

$91,000

$250,000

$199,000

$51,000

$153,000

$113,000

$40,000

128

Hospital

$35,000

$38,000

($3,000)

0

0

0

$35,000

$38,000

($3,000)

130

Office Building

$106,000

$81,000

$25,000

0

0

0

$106,000

$81,000

$25,000

Totals

$1,123,000

$876,000

$247,000

$621,000

$515,000

$106,000

$502,000

$361,000

$141,000

Notes

1 Contract Totals for Revenues Earned, Cost of Revenues and Gross Profit (Loss) would be used for the tax return if on the Completed Contract Method.

2 Before January 1, 2002

3 Year Ended December 31, 2002

Exhibit 6E XYZ Corporation Schedule 3 – Contracts in Process Year Ended December 31, 2002
# Revenues Estimated Gross Profit (Loss) Revenues Earned 1 Cost of Revenues 1 Gross Profit (Loss) 1 Billed to Date 1 Estimated Cost to Complete 1

119

1,275,000

210,000

1,228,310

1,026,000

202,310

1,225,000

39,000

120

211,000

(10,000)

107,887

113,000

(5,113)

106,000

108,000

123

53,000

15,000

43,237

31,000

12,237

46,000

7,000

124

258,000

50,000

129,000

104,000

25,000

117,000

104,000

125

218,000

40,000

79,607

65,000

14,607

74,000

113,000

126

85,000

13,000

47,222

40,000

7,222

43,000

32,000

129

220,000

42,000

181,685

147,000

34,685

180,000

31,000

131

160,000

38,000

28,852

22,000

6,852

30,000

100,000

133

152,000

1,000

37,245

37,000

245

39,000

114,000

 

2,632,000

399,000

1,883,045

1,585,000

298,045

1,860,000

648,000

Notes

1 Amounts are from inception of the contract to December 31, 2002.

Exhibit 6E XYZ Corporation Schedule 3 – Contracts in Process Year Ended December 31, 2002 (continued)
# Revenues Estimated Gross Profit (Loss) Revenues Earned 2 Cost of Revenues 2 Gross Profit (Loss) 2 Cost and Estimated Earnings in Excess of Billings 3 Billings in Excess of Costs and Estimated Earnings 3 Revenues Earned 4 Cost of Revenues 4 Gross Profit (Loss) 4 Percentage Complete 4

119

1,275,000

210,000

1,049,000

880,000

169,000

3,310

0

179,310

146,000

33,310

96.34%

120

211,000

(10,000)

0

0

0

1,887

0

211,000

221,000

(10,000)

51.13%

123

53,000

15,000

0

0

0

0

2,763

43,237

31,000

12,237

81.58%

124

258,000

50,000

0

0

0

12,000

0

129,000

104,000

25,000

50.00%

125

218,000

40,000

0

0

0

5,607

0

79,607

65,000

14,607

36.52%

126

85,000

13,000

0

0

0

4,222

0

47,222

40,000

7,222

55.56%

129

220,000

42,000

0

0

0

1,685

0

181,685

147,000

34,685

82.58%

131

160,000

38,000

0

0

0

0

1,148

28,852

22,000

6,852

18.03%

133

152,000

1,000

0

0

0

0

1,755

37,245

37,000

245

24.50%

 

2,632,000

399,000

1,049,000

880,000

169,000

28,711

5,666

937,159

813,000

124,159

 

Notes

2 Amounts are from before January 1, 2002.

3 Amounts are at December 31, 2002 (Balance Sheet Accounts).

4 Amounts are for the Year Ended December 31, 2002.

Audit Considerations:

  1. Job # 120 has a total estimated loss of (10,000) – the full loss is being reported for financial purposes. However, the job is only 51.13% complete. Thus, there should be a Schedule M-1 adjustment from book to tax.
  2. Where is Job # 132? – Not located on this schedule or the completed contract schedule.
  3. Job # 133 has an unusually low gross profit compared to other jobs. Why?
Page Last Reviewed or Updated: 2012-12-27