NOTE: This document is not an official pronouncement of the law or the position of the Service and can not be used, cited, or relied upon as such. This guide is current through the publication date. Since changes may have occurred after the publication date that would affect the accuracy of this document, no guarantees are made concerning the technical accuracy after the publication date.
Table of Contents
Chapter 10 / Appendix
Chapter 11: Contractor Square Foot Costs
- Introduction
- Division 1 - Site Work
- Division 2 - Foundations
- Division 3 - Framing
- Division 4 - Exterior Walls
- Division 5 - Roofing
- Division 6 - Interiors
- Division 7 - Specialties
- Division 8 - Mechanical
- Division 9 - Electrical
- Division 10 - Installing Contractor’s Overhead and Profit
- Audit Issues and Examination Techniques
Introduction
Latest estimates put the Federal tax gap at $345 billion and growing. The tax gap is equivalent to a noncompliance rate of 16.3%. Of this amount, $285 billion is attributable to underreporting of business income of which $68 billion is attributable to sole-proprietors (Individual Income Tax, Form 1040, Schedule C). This amount represents the single largest source of the entire tax gap and is a direct result of little or no information reporting. Consequently, matching of income received to income reported cannot be performed.
In addressing the tax gap attributable to the construction industry, residential construction is of particular interest because this group of taxpayers accounts for 73% of the return filings but reports only 10% of the gross receipts. It is imperative that steps are taken to ensure that only the most noncompliant returns enter the examination stream and that appropriate issues, specifically underreporting of income, are examined in a quality manner. Of particular interest are cash intensive businesses. The Service is especially concerned with sole-proprietorships because they often lack internal controls and cash can easily go unreported. In addition, records can be either non-existent or inadequate. For example, cash receipts may not be deposited into the business bank account.
For this purpose, it is important to pursue alternative methods of addressing the underreporting of business income on residential construction returns. This can be achieved, in part, by utilizing innovative methodologies such as Residential Square Foot Costs and the Market-based Profit Markup when warranted. These methods are efficient and effective at estimating profit when taxpayers are not cooperative or their books and records are either non-existent or inadequate.
Material in this chapter is used with permission from Means Contractor’s Pricing Guide: Residential Square Foot Costs, 2007. Copyright Reed Construction Data, Kingston, MA 781-585-7880: All rights reserved.
It uses an Assemblies or sometimes referred to as systems format grouping all the functional elements of residential construction into nine construction divisions. Costs shown in the Means guide is based on national averages for materials and installation; however, material costs include a standard 10% markup for profit. These costs are national average material costs for January 2007 and include delivery to the job site. Installation costs include labor and equipment, plus a markup of 70.6% for the installing contractor’s overhead and profit.
“Costs per square foot” estimate for commonly constructed systems within the residential construction industry. You can arrive at a more accurate estimate by adding, removing or adjusting items to the system estimate to reflect the actual specifications of the work performed. These costs can also be adjusted to a specific location by applying the appropriate Location Factor. As noted in that section, simply multiply the cost by the location factor for a specific city. State and postal zip code number data is arranged alphabetically. For a city that is not listed, use the factor for a nearby city with similar economic characteristics. In summary, total project costs can be adjusted to over 900 locations throughout the U.S. and Canada. See the location factors section in this chapter.
Division 1 – Site Work
Footing Excavation:Reserved.
Foundation Excavation:Reserved.
Utility Trenching:Reserved.
Sidewalk:Sidewalk systems can be constructed using asphalt, concrete or brick pavers. Three-foot wide concrete sidewalk systems are the most common. These concrete sidewalk systems may include gravel fill, compact fill, hand grading, concrete walking surface and brick edging. The concrete used is 3000 pounds per square inch or “p.s.i.”
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Gravel Fill (4" deep) | 0.001 | $0.34 | $0.03 | $0.37 |
| Compact Fill |
|
| $0.01 | $0.01 |
| Hand Grade | 0.004 |
| $0.14 | $0.14 |
| Concrete (4" thick} | 0.040 | $1.91 | $1.54 | $3.45 |
| Edging (brick laid on edge) | 0.079 | $1.61 | $3.08 | $4.69 |
| TOTAL | 0.124 | $3.86 | $4.80 | $8.66 |
Driveway:
Driveway systems can be constructed using asphalt, concrete or brick pavers. Ten-foot wide concrete driveway systems are the most common. These concrete driveway systems may include gravel fill, compact fill, hand grading, concrete surface and brick edging. The concrete used is 3000 pounds per square inch or “p.s.i.”
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Excavation (10' wide and 6" deep) |
|
| $0.03 | $0.03 |
| Crushed Stone (6" base) | 0.001 | $0.76 | $0.08 | $0.84 |
| Hand Grade Base | 0.004 | $0.14 | $0.14 | |
| Concrete (4" thick} | 0.040 | $1.91 | $1.54 | $3.45 |
| Edging (brick laid on edge) | 0.024 | $0.48 | $0.92 | $1.40 |
| TOTAL | 0.069 | $3.15 | $2.71 | $5.86 |
Septic:
Reserved.
Chain Link Fence:Reserved.
Wood Fence:Reserved.
Division 2 - Foundations
Footing:Footing systems are constructed concrete. The thickness and widths can vary. These concrete systems include placing concrete via direct chute, forms, reinforcement bars, beveled keyway and dowel bars. The concrete commonly used is 3000 pounds per square inch or “p.s.i.”
| System Description | Labor Hours | Cost Per Linear Foot Materials | Cost Per Linear Foot Installation | Total |
|---|---|---|---|---|
| 8" x 18" Concrete (3000 psi via Direct Chute) | 0.016 | $4.56 | $0.56 | $5.12 |
| Footing Forms (4 Uses) | 0.103 | $0.86 | $3.87 | $4.73 |
| Reinforcing Bars 1/2" Diameter | 0.011 | $0.70 | $0.52 | $1.22 |
| 2" x 4" Beveled Keyway (4 Uses) | 0.015 | $0.22 | $0.66 | $0.88 |
| 2' Long 1/2" Diameter Dowel Bars (4 Uses) 6" OC | 0.006 | $0.12 | $0.27 | $0.39 |
| TOTAL | 0.151 | $6.46 | $5.88 | $12.34 |
| 12" x 24" Concrete (3000 psi via Direct Chute) | 0.028 | $7.98 | $0.98 | $8.96 |
| Footing Forms (4 Uses) | 0.155 | $1.30 | $5.82 | $7.12 |
| Reinforcing Bars 1/2" Diameter | 0.011 | $0.70 | $0.52 | $1.22 |
| 2" x 4" Beveled Keyway (4 Uses) | 0.015 | $0.22 | $0.66 | $0.88 |
| 2' Long 1/2" Diameter Dowel Bars (4 Uses) 6" OC | 0.006 | $0.12 | $0.27 | $0.39 |
| TOTAL | 0.215 | $10.32 | $8.25 | $18.57 |
| 12" x 36" Concrete (3000 psi via Direct Chute) | 0.044 | $12.54 | $1.53 | $14.07 |
| Footing Forms (4 Uses) | 0.155 | $1.30 | $5.82 | $7.12 |
| Reinforcing Bars 1/2" Diameter | 0.011 | $0.70 | $0.52 | $1.22 |
| 2" x 4" Beveled Keyway (4 Uses) | 0.015 | $0.22 | $0.66 | $0.88 |
| 2' Long 1/2" Diameter Dowel Bars (4 Uses) 6" OC | 0.006 | $0.12 | $0.27 | $0.39 |
| TOTAL | 0.231 | $14.88 | $8.80 | $23.68 |
Block Wall:
Block wall systems are constructed using concrete blocks, masonry reinforcements, parging with Portland cement, damp proofing, insulation, grout, anchor bolts and sill plates. The costs in this system are based on square foot of the wall. Do not subtract for window or door openings.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 8" Concrete Block (8" x 16" x 8") | 0.094 | $2.70 | $3.76 | $6.46 |
| Masonry Reinforcing (Every Second Course) | 0.002 | $0.17 | $0.09 | $0.26 |
| Parging (1 Coat Plastering with Portland Cement) | 0.014 | $0.25 | $0.58 | $0.83 |
| Damp Proofing (1 Coat Bituminous Coating) | 0.012 | $0.14 | $0.48 | $0.62 |
| Insulation ( 1" Rigid Polystyrene) | 0.010 | $0.52 | $0.44 | $0.96 |
| Grout (Pumped Solid) | 0.059 | $1.20 | $2.31 | $3.51 |
| Anchor Bolts ( 1/2" Diameter, 8" Long, 4' OC) | 0.002 | $0.05 | $0.11 | $0.16 |
| Sill Plate (2" x 4" Treated) | 0.007 | $0.15 | $0.32 | $0.47 |
| TOTAL | 0.200 | $5.18 | $8.09 | $13.27 |
| 12" Concrete Block (8" x 16" x 12") | 0.160 | $3.77 | $6.20 | $9.97 |
| Masonry Reinforcing (Every Second Course) | 0.003 | $0.19 | $0.14 | $0.33 |
| Parging (1 Coat Plastering with Portland Cement) | 0.014 | $0.25 | $0.58 | $0.83 |
| Damp Proofing (1 Coat Bituminous Coating) | 0.012 | $0.14 | $0.48 | $0.62 |
| Insulation ( 1" Rigid Polystyrene) | 0.01 | $0.52 | $0.44 | $0.96 |
| Grout (Pumped Solid) | 0.063 | $1.96 | $2.46 | $4.42 |
| Anchor Bolts ( 1/2" Diameter, 8" Long, 4' OC) | 0.002 | $0.05 | $0.11 | $0.16 |
| Sill Plate (2" x 4" Treated) | 0.007 | $0.15 | $0.32 | $0.47 |
| TOTAL | 0.271 | $7.03 | $10.73 | $17.76 |
Concrete Wall:
Concrete wall systems are constructed using concrete, reinforcement fabric, damp proofing, insulation, anchor bolts and sill plates. The costs in this system are based on square foot of the wall. Do not subtract for window or door openings. The costs assume a 4' high wall.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 8" Concrete (3000 psi 8" Thick) | 0.013 | $2.85 | $0.46 | $3.31 |
| Forms (Prefabricated Plywood 4 Uses per Month) | 0.076 | $1.46 | $2.92 | $4.38 |
| Light Reinforcement (Rebar) | 0.004 | $0.34 | $0.17 | $0.51 |
| Damp Proofing (2 Coats Brushed On) | 0.016 | $0.28 | $0.64 | $0.92 |
| Rigid Insulation ( 1" Polystyrene) | 0.010 | $0.52 | $0.44 | $0.96 |
| Anchor Bolts ( 1/2" Diameter, 12" Long, 4' OC) | 0.003 | $0.09 | $0.11 | $0.20 |
| Sill Plate (2" x 4" Treated) | 0.007 | $0.15 | $0.32 | $0.47 |
| TOTAL | 0.129 | $5.69 | $5.06 | $10.75 |
| 12" Concrete (3000 psi 12" Thick) | 0.019 | $4.56 | $0.67 | $5.23 |
| Forms (Prefabricated Plywood 4 Uses per Month) | 0.076 | $1.46 | $2.92 | $4.38 |
| Light Reinforcement (Rebar) | 0.005 | $0.51 | $0.26 | $0.77 |
| Damp Proofing (2 Coats Brushed On) | 0.016 | $0.28 | $0.64 | $0.92 |
| Rigid Insulation ( 1" Polystyrene) | 0.01 | $0.52 | $0.44 | $0.96 |
| Anchor Bolts ( 1/2" Diameter, 12" Long, 4' OC) | 0.003 | $0.09 | $0.11 | $0.20 |
| Sill Plate (2" x 4" Treated) | 0.007 | $0.15 | $0.32 | $0.47 |
| TOTAL | 0.136 | $7.57 | $5.36 | $12.93 |
Wood Wall Foundation:
Reserved.
Floor Slab:Floor slabs are constructed with concrete. These concrete slab systems include concrete, gravel, polyethylene vapor barrier, edge forms, welded wire fabric and a steel trowel finish. The concrete used is 3000 pounds per square inch or “p.s.i.” The slab costs are based on a cost per square foot of floor area.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 4" Concrete via Direct Chute (3000 psi 4" Thick) | 0.005 | $1.37 | $0.19 | $1.56 |
| Bank Run Gravel ( 4" Deep) | 0.001 | $0.38 | $0.04 | $0.42 |
| Polyethylene Vapor Barrier (.006" Thick) | 0.002 | $0.05 | $0.09 | $0.14 |
| Edge Forms (Expansion Material) | 0.005 | $0.03 | $0.20 | $0.23 |
| Welded Wire Fabric, 6 x 6, 10/10 (W1.4/W1.4) | 0.005 | $0.15 | $0.25 | $0.40 |
| Steel Trowel Finish | 0.015 |
| $0.58 | $0.58 |
| TOTAL | 0.033 | $1.98 | $1.35 | $3.33 |
| 6" Concrete via Direct Chute (3000 psi 4" Thick) | 0.008 | $2.17 | $0.29 | $2.46 |
| Bank Run Gravel ( 4" Deep) | 0.001 | $0.38 | $0.04 | $0.42 |
| Polyethylene Vapor Barrier (.006" Thick) | 0.002 | $0.05 | $0.09 | $0.14 |
| Edge Forms (Expansion Material) | 0.005 | $0.03 | $0.20 | $0.23 |
| Welded Wire Fabric, 6 x 6, 10/10 (W1.4/W1.4) | 0.005 | $0.15 | $0.25 | $0.40 |
| Steel Trowel Finish | 0.015 |
| $0.58 | $0.58 |
| TOTAL | 0.036 | $2.78 | $1.45 | $4.23 |
Division 3 - Framing
Floor:Generally, wood floor framing systems include joists, bridging, box sills, concrete filled steel column 4” diameter, girder (built up from three studs), sheathing, and furring.
Joists can be constructed using #2 or better wood pine studs, composite wood joists, or open web joists.
Wood Studs: Wood pine studs can be 2” x 4”, 2” x 6”, 2” x 8”, 2” x 10”or 2” x 12” that are placed at 12” or 16” On Center (OC”). The most common wood stud floor systems use 2” x 8”, 2” x 10” or 2” x 12” joists placed at 16” OC. Bridging can be accomplished using wood, metal or compression type material. The most commonly used is a pair of 1” x 3” boards placed at 6' OC. Box sills are constructed using the same type and size of wood pine studs. If girders are required, they can be 3 pieces of wood spiked together, solid wood or steel. When 3 pieces or wood are spiked together, 2” x 8”, 2” x 10” or 2” x 12” are commonly used. Solid wood used as girders are 3” x 8”, 3” x 10”, 3” x12”, 4” x 8”, 4” x 10” or 4” x 12”. Wide flange steel girders with fabrication are bolted. Commonly used steel girder sizes are 5”, 6”, 8” 10” or 12” deep. Plywood or boards can be used as sheathing. If plywood is used, it is usually CDX exterior grade and either ½”, 5/8” or ¾” thick. If boards are used, 1” x 8” or 1” x 10” boards can be laid in the regular manner or it may be laid diagonally. Furring is accomplished by using 1” x 3” boards at 12”, 16” or 24” OC with 16” OC being the most common.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 2" x 8" Wood Joists, 2" x 8", 16" OC | 0.015 | $0.92 | $0.63 | $1.55 |
| Bridging, 1" x 3", 6' OC | 0.005 | $0.03 | $0.21 | $0.24 |
| Box Sills, 2" x 8" | 0.002 | $0.14 | $0.09 | $0.23 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 8" | 0.013 | $0.34 | $0.58 | $0.92 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.072 | $2.45 | $3.14 | $5.59 |
| 2" x 10" Wood Joists, 2" x 10", 16" OC | 0.018 | $1.31 | $0.78 | $2.09 |
| Bridging, 1" x 3", 6' OC | 0.005 | $0.03 | $0.21 | $0.24 |
| Box Sills, 2" x 10" | 0.003 | $0.20 | $0.12 | $0.32 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 10" | 0.014 | $0.49 | $0.62 | $1.11 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.077 | $3.05 | $3.36 | $6.41 |
| 2" x 12" Wood Joists, 2" x 12", 16" OC | 0.018 | $1.57 | $0.80 | $2.37 |
| Bridging, 1" x 3", 6' OC | 0.005 | $0.03 | $0.21 | $0.24 |
| Box Sills, 2" x 12" | 0.003 | $0.24 | $0.12 | $0.36 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 12" | 0.015 | $0.59 | $0.65 | $1.24 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.078 | $3.45 | $3.41 | $6.86 |
Composite Wood Joists: Composite wood joists are prefabricated and can be 9 ½”, 11 ½, 14”, or 16” deep with a 15', 18' or 22' span that are placed at 12” or 16” OC. The most common composite wood joist (CWJ) floor systems use CWJ's that are 9 ½”, 11 ½, 14” deep and a 15', 18' or 22' span. The CWJ's are placed at 16” OC. Temporary strut lines using 1” x 4” boards placed at 8' OC are used to keep the CWJ's in place while framing. Bridging is not required when using CWJ's. In lieu of box sills, CWJ's of the same depth are used as rim joists to close off the two open ends. If girders are required, they can be 3 pieces of wood spiked together, solid wood or steel. When 3 pieces or wood are spiked together, 2” x 8”, 2” x 10” or 2” x 12” are commonly used. Solid wood used as girders are 3” x 8”, 3” x 10”, 3” x12”, 4” x 8”, 4” x 10” or 4” x 12”. Wide flange steel girders with fabrication are bolted. Commonly used steel girder sizes are 5”, 6”, 8” 10” or 12” deep. Plywood or boards can be used as sheathing. If plywood is used, it is usually CDX exterior grade and either ½”, 5/8” or ¾” thick. If boards are used, 1” x 8” or 1” x 10” boards can be laid in the regular manner or it may be laid diagonally. Furring is accomplished by using 1” x 3” boards at 12”, 16” or 24” OC with 16” OC being the most common.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Composite Wood Joists, 9 1/2", 16" OC, 15' Span | 0.018 | $2.05 | $0.78 | $2.83 |
| Temporary Strut Line, 1" x 4", 8' OC | 0.003 | $0.07 | $0.14 | $0.21 |
| CWJ Rim Joist, 9 1/2" | 0.003 | $0.31 | $0.12 | $0.43 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 8" | 0.013 | $0.34 | $0.58 | $0.92 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC |
| $0.00 | $0.00 | $0.00 |
| TOTAL | 0.051 | $3.54 | $2.25 | $5.79 |
| Composite Wood Joists, 11 1/2", 16" OC, 18' Span | 0.018 | $2.18 | $0.80 | $2.98 |
| Temporary Strut Line, 1" x 4", 8' OC | 0.003 | $0.07 | $0.14 | $0.21 |
| CWJ Rim Joist, 11 1/2" | 0.003 | $0.33 | $0.12 | $0.45 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 10" | 0.014 | $0.49 | $0.62 | $1.11 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC |
| $0.00 | $0.00 | $0.00 |
| TOTAL | 0.052 | $3.84 | $2.31 | $6.15 |
| Composite Wood Joists, 14", 16" OC, 22' Span | 0.020 | $2.55 | $0.85 | $3.40 |
| Temporary Strut Line, 1" x 4", 8' OC | 0.003 | $0.07 | $0.14 | $0.21 |
| CWJ Rim Joist, 14" | 0.003 | $0.38 | $0.13 | $0.51 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 12" | 0.015 | $0.59 | $0.65 | $1.24 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC |
| $0.00 | $0.00 | $0.00 |
| TOTAL | 0.055 | $4.36 | $2.40 | $6.76 |
Open Web Joists: Open web joists are prefabricated and can be 12”, 14”, 16” or 18” deep with a 21', 22', or 24' span that are placed at 12” or 16” OC. The most common open web joist (OWJ) floor systems are OWJ's that are 12”, 14” or 16” deep, have a 21', 22' or 24' span and are placed at 16” OC. In lieu of either box sills or CWJ rim joists, a continuous ribbing using 2” x 4” studs is used. Although not as common, 2” x 6”, 2” x 8”, 2” x 10” or 2” x 12” boards can be used. If girders are required, they can be 3 pieces of wood spiked together, solid wood or steel. When 3 pieces or wood are spiked together, 2” x 8”, 2” x 10” or 2” x 12” are commonly used. Solid wood used as girders are 3” x 8”, 3” x 10”, 3” x12”, 4” x 8”, 4” x 10” or 4” x 12”. Wide flange steel girders with fabrication are bolted. Commonly used steel girder sizes are 5”, 6”, 8” 10” or 12” deep. Plywood or boards can be used as sheathing. If plywood is used, it is usually CDX exterior grade and either ½”, 5/8” or ¾” thick. If boards are used, 1” x 8” or 1” x 10” boards can be laid in the regular manner or it may be laid diagonally. Furring is accomplished by using 1” x 3” boards at 12”, 16” or 24” OC with 16” OC being the most common.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Open Web Joists, 12" deep, 16" OC, 21' Span | 0.018 | $2.00 | $0.80 | $2.80 |
| Continuous Ribbing, 2" x 4" | 0.002 | $0.06 | $0.08 | $0.14 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 8" | 0.013 | $0.34 | $0.58 | $0.92 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.070 | $3.42 | $3.09 | $6.51 |
| Open Web Joists, 14" deep, 16" OC, 22' Span | 0.020 | $2.33 | $0.85 | $3.18 |
| Continuous Ribbing, 2" x 4" | 0.002 | $0.06 | $0.08 | $0.14 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 10" | 0.014 | $0.49 | $0.62 | $1.11 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.073 | $3.90 | $3.18 | $7.08 |
| Open Web Joists, 16" deep, 16" OC, 24' Span | 0.021 | $2.43 | $0.90 | $3.33 |
| Continuous Ribbing, 2" x 4" | 0.002 | $0.06 | $0.08 | $0.14 |
| Concrete Filled Steel Column, 4" Diameter | 0.002 | $0.12 | $0.11 | $0.23 |
| Girder, Built Up From Three 2" x 12" | 0.015 | $0.59 | $0.65 | $1.24 |
| Sheathing, Plywood, Subfloor, 5/8" CDX | 0.012 | $0.65 | $0.52 | $1.17 |
| Furring, 1" x 3", 16" OC | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.075 | $4.10 | $3.26 | $7.36 |
Exterior Wall:
Generally, exterior wood wall framing systems include studs, plates, corner bracing and sheathing.
Exterior walls can be constructed using #2 or better wood pine 2” x 4”, 2” x 6” or 2” x 8” studs placed at 12”, 16”, 24” or 32” OC. The most common exterior wall systems use 2” x 4” or 2” x 6” studs placed at 16” or 24” OC. Plates are constructed using #2 or better wood pine 2” x 4”, 2” x 6” or 2” x 8” studs. Top plates doubled using two studs. A single stud is used for the bottom plate. Let-in corner bracing can be accomplished using 1” x 6” boards or “T” shape steel brackets placed at 12”, 16”, 24” or 32” OC. Sheathing materials may be made of plywood, boards, wood fiber, polystyrene or fiberglass. If plywood, CDX 3/8”, ½”, 5/8” or ¾” thick can be used with ½” thickness being more common. If boards are used, 1” x 6” or 1” x 8” boards are laid regularly or diagonally. Regular wood fiber with no vapor barrier ½” or 5/8” thick can also be used. If the wood fiber is impregnated with asphalt, the thickness can be either 25/32” or ½”. Regular polystyrene that is either ¾” or 2” thick can be substituted. Foil faced fiberglass that 1” or 2” thick can also be used as sheathing. Additional costs are added to the total costs of the wall for each window and door opening will be discussed later. However, do not subtract the area of the openings.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 2" x 4" Studs, 16" OC | 0.015 | $0.41 | $0.63 | $1.04 |
| Plates, 2" x 4", double top, single bottom | 0.005 | $0.15 | $0.24 | $0.39 |
| Corner Bracing, let-in, 1" x 6" | 0.003 | $0.05 | $0.15 | $0.20 |
| Sheathing, 1/2" plywood, CDX | 0.011 | $0.52 | $0.50 | $1.02 |
| TOTAL | 0.034 | $1.13 | $1.52 | $2.65 |
| 2" x 4" Studs, 24" OC | 0.011 | $0.31 | $0.47 | $0.78 |
| Plates, 2" x 4", double top, single bottom | 0.005 | $0.15 | $0.24 | $0.39 |
| Corner Bracing, let-in, 1" x 6" | 0.002 | $0.05 | $0.10 | $0.15 |
| Sheathing, 1/2" plywood, CDX | 0.011 | $0.52 | $0.50 | $1.02 |
| TOTAL | 0.029 | $1.03 | $1.31 | $2.34 |
| 2" x 6" Studs, 16" OC | 0.016 | $0.63 | $0.70 | $1.33 |
| Plates, 2" x 6", double top, single bottom | 0.006 | $0.24 | $0.26 | $0.50 |
| Corner Bracing, let-in, 1" x 6" | 0.003 | $0.05 | $0.15 | $0.20 |
| Sheathing, 1/2" plywood, CDX | 0.014 | $0.52 | $0.62 | $1.14 |
| TOTAL | 0.039 | $1.44 | $1.73 | $3.17 |
| 2" x 6" Studs, 24" OC | 0.012 | $0.47 | $0.53 | $1.00 |
| Plates, 2" x 6", double top, single bottom | 0.006 | $0.24 | $0.26 | $0.50 |
| Corner Bracing, let-in, 1" x 6" | 0.002 | $0.05 | $0.10 | $0.15 |
| Sheathing, 1/2" plywood, CDX | 0.011 | $0.52 | $0.50 | $1.02 |
| TOTAL | 0.031 | $1.28 | $1.39 | $2.67 |
Window & Door Openings: Additional costs are added to the total costs of the exterior wall for each window and door opening. Additional costs are for each opening and have nothing to do with its square foot area. The additional costs are attributable to the construction of headers for each window and door opening. A header is a 2” x 6”, 2” x 8”, 2” x 10” or 2” x 12” stud that is doubled for increased strength that is needed to sustain the weight of the window or door. Caution: Do not subtract the area of the openings from the area of the exterior walls.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Headers, 2" x 6", Double, 2' Long | 0.178 | $2.52 | $7.75 | $10.27 |
| Headers, 2" x 6", Double, 3' Long | 0.267 | $3.78 | $11.65 | $15.43 |
| Headers, 2" x 6", Double, 4' Long | 0.356 | $5.05 | $15.50 | $20.55 |
| Headers, 2" x 6", Double, 5' Long | 0.444 | $6.30 | $19.40 | $25.70 |
| Headers, 2" x 8", Double, 4' Long | 0.376 | $7.35 | $16.40 | $23.75 |
| Headers, 2" x 8", Double, 5' Long | 0.471 | $9.20 | $20.50 | $29.70 |
| Headers, 2" x 8", Double, 6' Long | 0.565 | $11.05 | $24.50 | $35.55 |
| Headers, 2" x 8", Double, 8' Long | 0.753 | $14.70 | $33.00 | $47.70 |
| Headers, 2" x 10", Double, 4' Long | 0.400 | $10.50 | $17.45 | $27.95 |
| Headers, 2" x 10", Double, 6' Long | 0.600 | $15.70 | $26.00 | $41.70 |
| Headers, 2" x 10", Double, 8' Long | 0.800 | $21.00 | $35.00 | $56.00 |
| Headers, 2" x 10", Double, 10' Long | 1.000 | $26.00 | $43.50 | $69.50 |
| Headers, 2" x 12", Double, 8' Long | 0.853 | $25.00 | $37.50 | $62.50 |
| Headers, 2" x 12", Double, 12' Long | 1.280 | $37.50 | $56.00 | $93.50 |
Gable End Roof:
The more common gable end roof framing systems are constructed using 2” x 6” or 2” x 8” rafters placed at 16” OC with a 4/12 pitch, ceiling joists, ridge board, fascia board, rafter ties, soffit nailer (outrigger), sheathing and furring strips. The cost of this system is based on the square foot of plan area. All quantities have been adjusted accordingly.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Rafters ( 2" x 6", 16" OC, 4/12 Pitch) | 0.019 | $0.74 | $0.82 | $1.56 |
| Ceiling Joists ( 2" x 4", 16" OC) | 0.013 | $0.41 | $0.56 | $0.97 |
| Ridge Board ( 2" x 6" ) | 0.002 | $0.03 | $0.07 | $0.10 |
| Fascia Board ( 2" x 6" ) | 0.005 | $0.07 | $0.23 | $0.30 |
| Rafter Tie ( 1" x 4", 4' OC) | 0.001 | $0.03 | $0.05 | $0.08 |
| Soffit Nailer Outrigger ( 2" x 4", 24" OC) | 0.004 | $0.07 | $0.19 | $0.26 |
| Sheathing (Exterior Plywood CDX 1/2" Thick) | 0.013 | $0.61 | $0.59 | $1.20 |
| Furring Strips ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.080 | $2.21 | $3.51 | $5.72 |
| Rafters ( 2" x 8", 16" OC, 4/12 Pitch) | 0.020 | $1.08 | $0.85 | $1.93 |
| Ceiling Joists ( 2" x 6", 16" OC) | 0.013 | $0.63 | $0.56 | $1.19 |
| Ridge Board ( 2" x 8" ) | 0.002 | $0.05 | $0.08 | $0.13 |
| Fascia Board ( 2" x 8" ) | 0.007 | $0.09 | $0.31 | $0.40 |
| Rafter Tie ( 1" x 4", 4' OC) | 0.001 | $0.03 | $0.05 | $0.08 |
| Soffit Nailer Outrigger ( 2" x 4", 24" OC) | 0.004 | $0.07 | $0.19 | $0.26 |
| Sheathing (Exterior Plywood CDX 1/2" Thick) | 0.013 | $0.61 | $0.59 | $1.20 |
| Furring Strips ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.083 | $2.81 | $3.63 | $6.44 |
Truss Roof:
The more common truss roof framing systems are constructed using trusses placed at 16” or 24” OC with a 4/12 or 8/12 pitch and 26' span, fascia board, sheathing and furring strips. The cost of this system is based on the square foot of plan area. A one-foot overhand is included.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Truss (40# Loading, 16" OC, 4/12 Pitch, 26' Span) | 0.021 | $2.57 | $1.25 | $3.82 |
| Fascia Board ( 2" x 6" ) | 0.005 | $0.07 | $0.23 | $0.30 |
| Sheathing ( Exterior Plywood CDX 1/2" Thick) | 0.013 | $0.61 | $0.59 | $1.20 |
| Furring ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.062 | $3.50 | $3.07 | $6.57 |
| Truss (40# Loading, 16" OC, 8/12 Pitch, 26' Span) | 0.023 | $2.97 | $1.36 | $4.33 |
| Fascia Board ( 2" x 6" ) | 0.005 | $0.07 | $0.23 | $0.30 |
| Sheathing ( Exterior Plywood CDX 1/2" Thick) | 0.015 | $0.69 | $0.67 | $1.36 |
| Furring ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.066 | $3.98 | $3.26 | $7.24 |
| Truss (40# Loading, 24" OC, 4/12 Pitch, 26' Span) | 0.014 | $1.71 | $0.83 | $2.54 |
| Fascia Board ( 2" x 6" ) | 0.005 | $0.07 | $0.23 | $0.30 |
| Sheathing ( Exterior Plywood CDX 1/2" Thick) | 0.013 | $0.61 | $0.59 | $1.20 |
| Furring ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.055 | $2.64 | $2.65 | $5.29 |
| Truss (40# Loading, 24" OC, 8/12 Pitch, 26' Span) | 0.015 | $1.98 | $0.91 | $2.89 |
| Fascia Board ( 2" x 6" ) | 0.005 | $0.07 | $0.23 | $0.30 |
| Sheathing ( Exterior Plywood CDX 1/2" Thick) | 0.015 | $0.69 | $0.67 | $1.36 |
| Furring ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.058 | $2.99 | $2.81 | $5.80 |
Hip Roof:
The more common hip roof framing systems are constructed using 2” x 6” or 2” x 8” rafters placed at 16” OC with a 4/12 pitch, jack rafters, ceiling joists, fascia board, soffit nailer (outrigger), sheathing and furring strips. The cost of this system is based on the square foot of plan area. Measurement is area under the hip roof only. See gable roof system for added costs.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Hip Rafters ( 2" x 8", 4/12 Pitch) | 0.004 | $0.15 | $0.16 | $0.31 |
| Jack Rafters ( 2" x 6", 16" OC, 4/12 Pitch) | 0.038 | $0.90 | $1.66 | $2.56 |
| Ceiling Joists ( 2" x 6", 16" OC) | 0.013 | $0.63 | $0.56 | $1.19 |
| Fascia Board ( 2" x 8") | 0.016 | $0.20 | $0.68 | $0.88 |
| Soffit Nailer Outrigger ( 2" x 4", 24" OC) | 0.006 | $0.09 | $0.25 | $0.34 |
| Sheathing ( 1/2" Exterior Plywood CDX) | 0.018 | $0.82 | $0.79 | $1.61 |
| Furring Strips ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.118 | $3.04 | $5.10 | $8.14 |
| Hip Rafters ( 2" x 10", 4/12 Pitch) | 0.004 | $0.21 | $0.20 | $0.41 |
| Jack Rafters ( 2" x 8", 16" OC, 4/12 Pitch) | 0.047 | $1.32 | $2.03 | $3.35 |
| Ceiling Joists ( 2" x 6", 16" OC) | 0.013 | $0.63 | $0.56 | $1.19 |
| Fascia Board ( 2" x 8") | 0.012 | $0.16 | $0.53 | $0.69 |
| Soffit Nailer Outrigger ( 2" x 4", 24" OC) | 0.006 | $0.09 | $0.25 | $0.34 |
| Sheathing ( 1/2" Exterior Plywood CDX) | 0.018 | $0.82 | $0.79 | $1.61 |
| Furring Strips ( 1" x 3", 16" OC) | 0.023 | $0.25 | $1.00 | $1.25 |
| TOTAL | 0.123 | $3.48 | $5.36 | $8.84 |
Gambrel Roof:
Reserved.
Mansard Roof:Reserved.
Shed/Flat Roof:Reserved.
Gable Dormer:Reserved.
Shed Dormer:Reserved.
Partition:Generally, partition-framing systems include studs, plates and cross bracing.
Partitions can be constructed using #2 or better wood pine 2” x 4” or 2” x 6” studs placed at 12”, 16”, 24” or 32” OC. The most common exterior wall systems use 2” x 4” or 2” x 6” wood studs placed at 16” or 24” OC. Metal load bearing and non-load bearing studs can also be used. Metal load bearing studs are either 20 or 16 gauge galvanized steel studs placed at 24” OC. Metal non-load bearing studs are either 25 or 20 gauge galvanized steel studs placed at 24” OC. Both metal load bearing and non-load bearing studs come in 2 ½”, 3 5/8”, 4” or 6” widths. Plates are constructed using #2 or better wood pine 2” x 4”, 2” x 6” or 2” x 8” studs. Top plates doubled using two studs. A single stud is used for the bottom plate. Let-in cross bracing can be accomplished using 1” x 6” boards, “T” shape steel brackets, or steel straps placed at 12”, 16”, 24” or 32” OC.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| 2" x 4" Studs, 16" OC | 0.015 | $0.41 | $0.63 | $1.04 |
| Plates, 2" x 4", double top, single bottom | 0.005 | $0.15 | $0.24 | $0.39 |
| Cross Bracing, let-in, 1" x 6" | 0.004 | $0.06 | $0.19 | $0.25 |
| TOTAL | 0.024 | $0.62 | $1.06 | $1.68 |
| 2" x 4" Studs, 24" OC | 0.012 | $0.33 | $0.50 | $0.83 |
| Plates, 2" x 4", double top, single bottom | 0.005 | $0.15 | $0.24 | $0.39 |
| Corner Bracing, let-in, 1" x 6" | 0.003 | $0.06 | $0.12 | $0.18 |
| TOTAL | 0.020 | $0.54 | $0.86 | $1.40 |
| 2" x 6" Studs, 16" OC | 0.016 | $0.63 | $0.70 | $1.33 |
| Plates, 2" x 6", double top, single bottom | 0.006 | $0.24 | $0.26 | $0.50 |
| Cross Bracing, let-in, 1" x 6" | 0.004 | $0.06 | $0.19 | $0.25 |
| TOTAL | 0.026 | $0.93 | $1.15 | $2.08 |
| 2" x 6" Studs, 24" OC | 0.013 | $0.50 | $0.56 | $1.06 |
| Plates, 2" x 6", double top, single bottom | 0.006 | $0.24 | $0.26 | $0.50 |
| Cross Bracing, let-in, 1" x 6" | 0.003 | $0.06 | $0.12 | $0.18 |
| TOTAL | 0.022 | $0.80 | $0.94 | $1.74 |
Additional costs are added to the total costs of the wall for each window and door opening will be discussed later. However, do not subtract the area of the openings.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Headers, 2" x 6", Double, 2' Long | 0.178 | $2.52 | $7.75 | $10.27 |
| Headers, 2" x 6", Double, 3' Long | 0.267 | $3.78 | $11.65 | $15.43 |
| Headers, 2" x 6", Double, 4' Long | 0.356 | $5.05 | $15.50 | $20.55 |
| Headers, 2" x 6", Double, 5' Long | 0.444 | $6.30 | $19.40 | $25.70 |
| Headers, 2" x 8", Double, 4' Long | 0.376 | $7.35 | $16.40 | $23.75 |
| Headers, 2" x 8", Double, 5' Long | 0.471 | $9.20 | $20.50 | $29.70 |
| Headers, 2" x 8", Double, 6' Long | 0.565 | $11.05 | $24.50 | $35.55 |
| Headers, 2" x 8", Double, 8' Long | 0.753 | $14.70 | $33.00 | $47.70 |
| Headers, 2" x 10", Double, 4' Long | 0.400 | $10.50 | $17.45 | $27.95 |
| Headers, 2" x 10", Double, 6' Long | 0.600 | $15.70 | $26.00 | $41.70 |
| Headers, 2" x 10", Double, 8' Long | 0.800 | $21.00 | $35.00 | $56.00 |
| Headers, 2" x 10", Double, 10' Long | 1.000 | $26.00 | $43.50 | $69.50 |
| Headers, 2" x 12", Double, 8' Long | 0.853 | $25.00 | $37.50 | $62.50 |
| Headers, 2" x 12", Double, 12' Long | 1.280 | $37.50 | $56.00 | $93.50 |
Division 4 - Exterior Walls
Block Masonry Wall:Block wall systems are constructed using concrete blocks, masonry reinforcements, masonry insulation, stucco and masonry paint. The costs in this system are based on square foot of the wall. Do not subtract for window or door openings.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Concrete Block (6" x 8" x 16") | 0.100 | $1.96 | $3.99 | $5.95 |
| Masonry Reinforcing Strips (Every Other Course) | 0.002 | $0.14 | $0.08 | $0.22 |
| Furring (1" x 3", 16" OC) | 0.016 | $0.25 | $0.70 | $0.95 |
| Masonry Insulation (Poured Vermiculite) | 0.013 | $0.62 | $0.58 | $1.20 |
| Stucco (2 Coats) | 0.069 | $0.20 | $2.73 | $2.93 |
| Masonry Paint (2 Coats) | 0.016 | $0.20 | $0.61 | $0.81 |
| TOTAL | 0.216 | $3.37 | $8.69 | $12.06 |
| Concrete Block (8" x 8" x 16") | 0.107 | $2.14 | $4.26 | $6.40 |
| Masonry Reinforcing Strips (Every Other Course) | 0.002 | $0.14 | $0.08 | $0.22 |
| Furring (1" x 3", 16" OC) | 0.016 | $0.25 | $0.70 | $0.95 |
| Masonry Insulation (Poured Vermiculite) | 0.018 | $0.82 | $0.77 | $1.59 |
| Stucco (2 Coats) | 0.069 | $0.20 | $2.73 | $2.93 |
| Masonry Paint (2 Coats) | 0.016 | $0.20 | $0.61 | $0.81 |
| TOTAL | 0.228 | $3.75 | $9.15 | $12.90 |
| Concrete Block (12" x 8" x 16") | 0.141 | $3.18 | $5.50 | $8.68 |
| Masonry Reinforcing Strips (Every Other Course) | 0.003 | $0.16 | $0.11 | $0.27 |
| Furring (1" x 3", 16" OC) | 0.016 | $0.25 | $0.70 | $0.95 |
| Masonry Insulation (Poured Vermiculite) | 0.026 | $1.22 | $1.13 | $2.35 |
| Stucco (2 Coats) | 0.069 | $0.20 | $2.73 | $2.93 |
| Masonry Paint (2 Coats) | 0.016 | $0.20 | $0.61 | $0.81 |
| TOTAL | 0.271 | $5.21 | $10.78 | $15.99 |
Brick/Stone Veneer:
The most common brick or stone veneer systems are constructed using brick, wall ties, building paper and painted pine trim. The costs in this system are based on a square foot of wall area. Do not subtract area for window and door openings.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Brick (Select Common Running Bond) | 0.174 | $4.24 | $6.95 | $11.19 |
| Wall Ties ( 7/8" x 7", 22 Gauge) | 0.008 | $0.07 | $0.34 | $0.41 |
| Building Paper (Spunbonded Polypropylene) | 0.002 | $0.15 | $0.10 | $0.25 |
| Trim (Pine Painted) | 0.004 | $0.09 | $0.18 | $0.27 |
| TOTAL | 0.188 | $4.55 | $7.57 | $12.12 |
| Brick (Select Common Red Faced Running Bond) | 0.182 | $4.24 | $7.25 | $11.49 |
| Wall Ties ( 7/8" x 7", 22 Gauge) | 0.008 | $0.07 | $0.34 | $0.41 |
| Building Paper (Spunbonded Polypropylene) | 0.002 | $0.15 | $0.10 | $0.25 |
| Trim (Pine Painted) | 0.004 | $0.09 | $0.18 | $0.27 |
| TOTAL | 0.196 | $4.55 | $7.87 | $12.42 |
| Brick (Buff or Gray) | 0.182 | $4.48 | $7.25 | $11.73 |
| Wall Ties ( 7/8" x 7", 22 Gauge) | 0.008 | $0.07 | $0.34 | $0.41 |
| Building Paper (Spunbonded Polypropylene) | 0.002 | $0.15 | $0.10 | $0.25 |
| Trim (Pine Painted) | 0.004 | $0.09 | $0.18 | $0.27 |
| TOTAL | 0.196 | $4.79 | $7.87 | $12.66 |
| Field Stone Veneer | 0.223 | $6.20 | $8.91 | $15.11 |
| Wall Ties ( 7/8" x 7", 22 Gauge) | 0.008 | $0.07 | $0.34 | $0.41 |
| Building Paper (Spunbonded Polypropylene) | 0.002 | $0.15 | $0.10 | $0.25 |
| Trim (Pine Painted) | 0.004 | $0.09 | $0.18 | $0.27 |
| TOTAL | 0.237 | $6.51 | $9.53 | $16.04 |
Wood Siding:
Reserved.
Shingle Siding:Reserved.
Metal & Plastic Siding:Reserved.
Insulation:Reserved.
Double Hung Window:Reserved.
Casement Window:Reserved.
Awning Window:Reserved.
Sliding Window:Reserved.
Bow/Bay Window:Reserved.
Fixed Window:Reserved.
Entrance Door:Reserved.
Sliding Door:Reserved.
Residential Overhead Door:Reserved.
Aluminum Window:Reserved.
Storm Door & Window:
Reserved.
Shutters/Blinds:Reserved.
Division 5 - Roofing
Gable End Roofing:The more common gable end roofing systems are constructed using asphalt or cedar wood shingles, drip edge, building paper, ridge shingles, soffit and fascia, rake trim, gutter and downspouts. The prices in these systems are based on a square foot of plan area. All quantities have been adjusted accordingly.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Shingles ( Inorganic Class A, 210-235 lb/sq, 4/12 Pitch) | 0.017 | $0.55 | $0.70 | $1.25 |
| Drip Edge (Metal 5" Wide) | 0.003 | $0.07 | $0.13 | $0.20 |
| Building Paper (#15 Felt) | 0.002 | $0.06 | $0.07 | $0.13 |
| Ridge Shingles (Asphalt) | 0.001 | $0.07 | $0.04 | $0.11 |
| Soffit & Fascia (White Painted Aluminum, 1' Overhang) | 0.012 | $0.26 | $0.53 | $0.79 |
| Rake Rim ( 1" x 6") | 0.002 | $0.05 | $0.07 | $0.12 |
| Rake Trim (Prime and Paint) | 0.002 | $0.01 | $0.07 | $0.08 |
| Gutter (Seamless Aluminum Painted) | 0.006 | $0.17 | $0.27 | $0.44 |
| Downspouts (Aluminum Painted) | 0.002 | $0.06 | $0.08 | $0.14 |
| TOTAL | 0.047 | $1.30 | $1.96 | $3.26 |
| Shingles (18" Wood, Cedar No. 1 Perfections, 4/12 Pitch) | 0.035 | $2.21 | $1.52 | $3.73 |
| Drip Edge (Metal 5" Wide) | 0.003 | $0.07 | $0.13 | $0.20 |
| Building Paper (#15 Felt) | 0.002 | $0.06 | $0.07 | $0.13 |
| Ridge Shingles (Asphalt) | 0.001 | $0.14 | $0.05 | $0.19 |
| Soffit & Fascia (White Painted Aluminum, 1' Overhang) | 0.012 | $0.26 | $0.53 | $0.79 |
| Rake Rim ( 1" x 6") | 0.002 | $0.05 | $0.07 | $0.12 |
| Rake Trim (Prime and Paint) | 0.002 | $0.01 | $0.07 | $0.08 |
| Gutter (Seamless Aluminum Painted) | 0.006 | $0.17 | $0.27 | $0.44 |
| Downspouts (Aluminum Painted) | 0.002 | $0.06 | $0.08 | $0.14 |
| TOTAL | 0.065 | $3.03 | $2.79 | $5.82 |
Hip Roof Roofing:
The more common gable end roofing systems are constructed using asphalt or cedar wood shingles, drip edge, building paper, ridge shingles, soffit and fascia, rake trim, gutter and downspouts. The prices in these systems are based on a square foot of plan area. All quantities have been adjusted accordingly.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Asphalt Shingles (Inorganic Class A, 210-235 lb/sq, 4/12 Pitch) | 0.023 | $0.74 | $0.94 | $1.68 |
| Drip Edge (Metal 5" Wide) | 0.002 | $0.06 | $0.11 | $0.17 |
| Building Paper (#15 Felt) | 0.002 | $0.08 | $0.10 | $0.18 |
| Ridge Shingles (Asphalt) | 0.002 | $0.12 | $0.07 | $0.19 |
| Soffit & Fascia (White Painted Aluminum, 1' Overhang) | 0.017 | $0.37 | $0.76 | $1.13 |
| Gutter (Seamless Aluminum Painted) | 0.008 | $0.24 | $0.39 | $0.63 |
| Downspouts (Aluminum Painted) | 0.002 | $0.06 | $0.08 | $0.14 |
| TOTAL | 0.056 | $1.67 | $2.45 | $4.12 |
| Wood Shingles (18" Cedar No.1 Perfections, 5" Exp, 4/12 Pitch) | 0.047 | $2.94 | $2.03 | $4.97 |
| Drip Edge (Metal 5" Wide) | 0.002 | $0.06 | $0.11 | $0.17 |
| Building Paper (#15 Felt) | 0.002 | $0.08 | $0.10 | $0.18 |
| Ridge Shingles (Asphalt) | 0.002 | $0.25 | $0.09 | $0.34 |
| Soffit & Fascia (White Painted Aluminum, 1' Overhang) | 0.017 | $0.37 | $0.76 | $1.13 |
| Gutter (Seamless Aluminum Painted) | 0.008 | $0.24 | $0.39 | $0.63 |
| Downspouts (Aluminum Painted) | 0.002 | $0.06 | $0.08 | $0.14 |
| TOTAL | 0.080 | $4.00 | $3.56 | $7.56 |
Gambrel Roofing:
Reserved.
Mansard Roofing:Reserved.
Shed Roofing:Reserved.
Gable Dormer Roofing:Reserved.
Shed Dormer Roofing:Reserved.
Skylight/Skywindow:Reserved.
Built-up Roofing:Reserved.
Division 6 - Interiors
Drywall & Thincoat Wall:The most common drywall and thincoat wall systems involve gypsum wallboard, taping joints and corners, painting and baseboard trim. The costs in this system are based on a square foot of wall. Do not deduct for openings.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Gypsum Wallboard ( 1/2" Thick, Standard) | 0.008 | $0.35 | $0.35 | $0.70 |
| Finish (Taped & Finished Joints) | 0.008 | $0.04 | $0.35 | $0.39 |
| Corners (Taped & Finished, 32 L.F. per 12' x 12' Room) | 0.002 | $0.01 | $0.07 | $0.08 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| Paint Trim (To 6" Wide Primer & 1 Coat Enamel) | 0.001 | $0.01 | $0.05 | $0.06 |
| Trim (Baseboard) | 0.005 | $0.33 | $0.22 | $0.55 |
| TOTAL | 0.035 | $0.93 | $1.44 | $2.37 |
| Gypsum Wallboard ( 1/2" Thick, Thincoat Backer) | 0.008 | $0.35 | $0.35 | $0.70 |
| Thincoat Plaster | 0.011 | $0.09 | $0.44 | $0.53 |
| Corners (Taped & Finished, 32 L.F. per 12' x 12' Room) | 0.002 | $0.01 | $0.07 | $0.08 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| Paint Trim (To 6" Wide Primer & 1 Coat Enamel) | 0.001 | $0.01 | $0.05 | $0.06 |
| Trim (Baseboard) | 0.005 | $0.33 | $0.22 | $0.55 |
| TOTAL | 0.038 | $0.98 | $1.53 | $2.51 |
| Gypsum Wallboard ( 5/8" Thick, Standard) | 0.008 | $0.43 | $0.35 | $0.78 |
| Finish (Taped & Finished Joints) | 0.008 | $0.04 | $0.35 | $0.39 |
| Corners (Taped & Finished, 32 L.F. per 12' x 12' Room) | 0.002 | $0.01 | $0.07 | $0.08 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| Paint Trim (To 6" Wide Primer & 1 Coat Enamel) | 0.005 | $0.33 | $0.22 | $0.55 |
| Trim (Baseboard) | 0.001 | $0.01 | $0.05 | $0.06 |
| TOTAL | 0.035 | $1.01 | $1.44 | $2.45 |
Drywall & Thincoat Ceiling:
The most common drywall and thincoat ceiling systems involve gypsum wallboard, taping joints and corners, painting and baseboard trim. The costs in this system are based on a square foot of ceiling.
| System Description | Labor Hours | Cost Per Square Foot Materials | Cost Per Square Foot Installation | Total |
|---|---|---|---|---|
| Gypsum Wallboard ( 1/2" Thick, Standard) | 0.008 | $0.35 | $0.35 | $0.70 |
| Finish (Taped & Finished) | 0.008 | $0.04 | $0.35 | $0.39 |
| Corners (Taped & Finished, 12' x 12' Room) | 0.006 | $0.03 | $0.24 | $0.27 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| TOTAL | 0.033 | $0.61 | $1.34 | $1.95 |
| Gypsum Wallboard ( 1/2" Thick, Thincoat Backer) | 0.008 | $0.35 | $0.35 | $0.70 |
| Thincoat Plaster | 0.011 | $0.09 | $0.44 | $0.53 |
| Corners (Taped & Finished, 12' x 12' Room) | 0.006 | $0.03 | $0.24 | $0.27 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| TOTAL | 0.036 | $0.66 | $1.43 | $2.09 |
| Gypsum Wallboard ( 5/8" Thick, Water Resistant) | 0.008 | $0.43 | $0.35 | $0.78 |
| Finish (Taped & Finished) | 0.008 | $0.04 | $0.35 | $0.39 |
| Corners (Taped & Finished, 12' x 12' Room) | 0.006 | $0.03 | $0.24 | $0.27 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| TOTAL | 0.033 | $0.69 | $1.34 | $2.03 |
| Gypsum Wallboard ( 5/8" Thick, Standard) | 0.008 | $0.43 | $0.35 | $0.78 |
| Finish (Taped & Finished) | 0.008 | $0.04 | $0.35 | $0.39 |
| Corners (Taped & Finished, 32 L.F. per 12' x 12' Room) | 0.006 | $0.03 | $0.24 | $0.27 |
| Painting (Primer & 2 Coats) | 0.011 | $0.19 | $0.40 | $0.59 |
| TOTAL | 0.033 | $0.69 | $1.34 | $2.03 |
Plaster & Stucco Wall:
Reserved.
Plaster & Stucco Ceiling:Reserved.
Suspended Ceiling:Reserved.
Interior Door:Reserved.
Closet Door:Reserved.
Carpet:Reserved.
Flooring:Reserved.
Stairways:Reserved.
Division 7 - Specialties
Kitchen:Reserved.
Appliances:Reserved.
Bath Accessories:Reserved.
Masonry Fireplace:Reserved.
Prefabricated Fireplace:Reserved.
Greenhouse:Reserved.
Swimming Pool:Reserved.
Wood Deck:Reserved.
Division 8 - Mechanical
Two Fixture Lavatory:A common two-fixture lavatory system includes a water closet and lavatory that is either installed on a vanity or is wall-hung with plumbing in 2 walls (opposite from each other). The costs in this system are on a cost each basis. All necessary piping is included.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent (2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste (4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply (1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory (20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Vent (1 1/2" Diameter Drain Waste Vent Piping) | 0.901 | $24.00 | $39.40 | $63.40 |
| Rough-In Waste (2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Supply (1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Waste (4" Diameter Drain Waste Vent Piping) | 1.931 | $74.55 | $84.35 | $158.90 |
| Vent (2" Diameter Drain Waste Vent Piping) | 2.866 | $74.40 | $125.40 | $199.80 |
| Vanity Base Cabinet (2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $89.45 | $31.11 | $120.56 |
| TOTAL | 18.236 | $1,133.71 | $809.31 | $1,943.02 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron, Wall Hung, White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.901 | $24.00 | $39.40 | $63.40 |
| Rough-In Waste ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 1.931 | $74.55 | $84.35 | $158.90 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 2.866 | $74.40 | $125.40 | $199.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 17.167 | $914.26 | $768.70 | $1,682.96 |
Three Fixture Bathroom:
A common three-fixture lavatory system includes a water closet, bathtub and/or shower and lavatory that is installed on either a vanity or is wall-hung with plumbing in either 1 or 2 walls. The costs in this system are on a cost each basis. All necessary piping is included.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 1 Wall |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 1.655 | $63.90 | $72.30 | $136.20 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $70.76 | $31.11 | $101.87 |
| TOTAL | 22.586 | $2,035.62 | $1,007.11 | $3,042.73 |
| Lavatory Wall Hung Plumbing in 1 Wall |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Supply Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 1.655 | $63.90 | $72.30 | $136.20 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 21.517 | $1,834.86 | $966.50 | $2,801.36 |
The costs below are for a three-fixture bathroom system where the water closet and lavatory are constructed on one wall and the bathtub is constructed on another wall.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
| ||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 1.975 | $75.20 | $96.00 | $171.20 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.483 | $95.85 | $108.45 | $204.30 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $70.76 | $31.11 | $101.87 |
| TOTAL | 24.401 | $2,105.17 | $1,091.26 | $3,196.43 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.482 | $127.00 | $72.00 | $199.00 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 1.975 | $75.20 | $96.00 | $171.20 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.483 | $95.85 | $108.45 | $204.30 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 24.221 | $1,980.61 | $1,093.85 | $3,074.46 |
The costs below are for a three-fixture bathroom system where the water closet and bathtub are constructed on one wall and the lavatory is constructed on another wall.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 3.310 | $127.80 | $144.60 | $272.40 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $70.76 | $31.11 | $101.87 |
| TOTAL | 26.414 | $2,182.24 | $1,185.01 | $3,367.25 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 3.310 | $127.80 | $144.60 | $272.40 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 25.345 | $1,981.48 | $1,144.40 | $3,125.88 |
The costs below are for a three-fixture bathroom system where the water closet and a corner bathtub are constructed on one wall and the lavatory is constructed on another wall.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $1,825.00 | $159.00 | $1,984.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 3.310 | $127.80 | $144.60 | $272.40 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $89.45 | $31.11 | $120.56 |
| TOTAL | 26.414 | $3,195.93 | $1,185.01 | $4,380.94 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Bathtub (P.E. Cast Iron, 5' Long with Accessories, White) | 3.636 | $1,825.00 | $159.00 | $1,984.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 3.310 | $127.80 | $144.60 | $272.40 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 25.345 | $2,976.48 | $1,144.40 | $4,120.88 |
The costs below are for a three-fixture bathroom system where the water closet and shower are constructed on one wall and the lavatory is constructed on another wall. The fixtures are on opposite walls.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.200 | $380.00 | $140.00 | $520.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.225 | $6.00 | $9.85 | $15.85 |
| Rough-In Waste ( 2" Diameter Drain Waste Vent Piping) | 1.433 | $37.20 | $62.70 | $99.90 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 1.580 | $60.16 | $76.80 | $136.96 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.148 | $157.92 | $201.60 | $359.52 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.759 | $106.50 | $120.50 | $227.00 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 2.250 | $84.15 | $98.55 | $182.70 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $73.43 | $31.11 | $104.54 |
| TOTAL | 30.326 | $2,107.27 | $1,372.66 | $3,479.93 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.200 | $380.00 | $140.00 | $520.00 |
| Shower Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.225 | $6.00 | $9.85 | $15.85 |
| Rough-In Waste ( 2" Diameter Drain Waste Vent Piping) | 1.433 | $37.20 | $62.70 | $99.90 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 1.580 | $60.16 | $76.80 | $136.96 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.148 | $157.92 | $201.60 | $359.52 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.759 | $106.50 | $120.50 | $227.00 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 2.250 | $84.15 | $98.55 | $182.70 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 29.257 | $1,903.84 | $1,332.05 | $3,235.89 |
The costs below are for a three-fixture bathroom system where the water closet and lavatory are constructed on adjacent walls and the lavatory is constructed on the corner of the adjacent walls.
| System Description | Labor Hours | Cost Each Cost Each | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.200 | $380.00 | $140.00 | $520.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.225 | $6.00 | $9.85 | $15.85 |
| Rough-In Waste ( 2" Diameter Drain Waste Vent Piping) | 1.433 | $37.20 | $62.70 | $99.90 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 1.580 | $60.16 | $76.80 | $136.96 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.556 | $135.36 | $172.80 | $308.16 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 1.931 | $74.55 | $84.35 | $158.90 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $70.76 | $31.11 | $101.87 |
| TOTAL | 28.156 | $2,022.04 | $1,274.86 | $3,296.90 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( Wall Hung 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 1.803 | $48.00 | $78.80 | $126.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.200 | $380.00 | $140.00 | $520.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.225 | $6.00 | $9.85 | $15.85 |
| Rough-In Waste ( 2" Diameter Drain Waste Vent Piping) | 1.433 | $37.20 | $62.70 | $99.90 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 1.580 | $60.16 | $76.80 | $136.96 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 3.556 | $135.36 | $172.80 | $308.16 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 1.931 | $74.55 | $84.35 | $158.90 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 1.500 | $56.10 | $65.70 | $121.80 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 27.087 | $1,821.28 | $1,234.25 | $3,055.53 |
Four Fixture Bathroom:
The costs below are for a four-fixture bathroom system where the water closet and lavatory are constructed on one wall and the bathtub and shower are constructed on the opposite wall.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.333 | $845.00 | $146.00 | $991.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 4.507 | $120.00 | $197.00 | $317.00 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Bathtub (P.E. Cast Iron, 5' Long with Fittings, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.148 | $157.92 | $201.60 | $359.52 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.759 | $106.50 | $120.50 | $227.00 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 3.250 | $121.55 | $142.35 | $263.90 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $70.76 | $31.11 | $101.87 |
| TOTAL | 39.143 | $3,608.71 | $1,768.86 | $5,377.57 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( Wall Hung 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.333 | $845.00 | $146.00 | $991.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 4.507 | $120.00 | $197.00 | $317.00 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Bathtub (P.E. Cast Iron, 5' Long with Fittings, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.148 | $157.92 | $201.60 | $359.52 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.759 | $106.50 | $120.50 | $227.00 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 3.250 | $121.55 | $142.35 | $263.90 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 38.074 | $3,407.95 | $1,728.25 | $5,136.20 |
The costs below are for a four-fixture bathroom system where the water closet and bathtub are constructed on one wall. The vanity is constructed on the opposite wall. The shower is constructed on the corner of the wall that is common with the lavatory.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Lavatory With Vanity Plumbing in 2 Walls |
|
|
|
|
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", P.E. Cast Iron White) | 2.500 | $242.00 | $109.00 | $351.00 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.333 | $845.00 | $146.00 | $991.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 4.507 | $120.00 | $197.00 | $317.00 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Bathtub (P.E. Cast Iron, 5' Long with Fittings, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.939 | $188.00 | $240.00 | $428.00 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 4.138 | $159.75 | $180.75 | $340.50 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 4.500 | $168.30 | $197.10 | $365.40 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.000 | $249.00 | $43.50 | $292.50 |
| Vanity Top (Plastic & Laminated, Square Edge) | 0.712 | $73.43 | $31.11 | $104.54 |
| TOTAL | 42.563 | $3,741.46 | $1,922.26 | $5,663.72 |
| Lavatory Wall Hung Plumbing in 2 Walls |
| |||
| Water Closet (Floor Mounted, 2 Piece, Close Coupled, White) | 3.019 | $201.00 | $132.00 | $333.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( Wall Hung 20" x 18", P.E. Cast Iron White) | 2.000 | $305.00 | $87.50 | $392.50 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.333 | $845.00 | $146.00 | $991.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 4.507 | $120.00 | $197.00 | $317.00 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 3.161 | $120.32 | $153.60 | $273.92 |
| Bathtub (P.E. Cast Iron, 5' Long with Fittings, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.939 | $188.00 | $240.00 | $428.00 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 4.138 | $159.75 | $180.75 | $340.50 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 4.500 | $168.30 | $197.10 | $365.40 |
| Carrier (Steel for Studs, No Arms) | 1.143 | $56.00 | $55.50 | $111.50 |
| TOTAL | 41.494 | $3,538.03 | $1,881.65 | $5,419.68 |
Five Fixture Bathroom:
The costs below are for a five-fixture bathroom system where the water closet and lavatory are constructed on one wall, the bathtub is constructed on an adjacent wall (corner) and the shower is constructed on the corner of the wall opposite the bathtub or adjacent to the lavatory.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Bathroom with Shower, Bathtub, Lavatories in Vanity |
|
|
|
|
| Water Closet (Floor Mounted, 1 Piece Combination, White) | 3.019 | $810.00 | $132.00 | $942.00 |
| Rough-In Vent ( 2" Diameter Drain Waste Vent Piping) | 0.955 | $24.80 | $41.80 | $66.60 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 0.828 | $31.95 | $36.15 | $68.10 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.593 | $22.56 | $28.80 | $51.36 |
| Lavatory ( 20" x 18", Vitreous China Oval with Fittings, White) | 5.926 | $582.00 | $260.00 | $842.00 |
| Shower (Steel Enameled, Stone Base, Corner, White) | 3.333 | $845.00 | $146.00 | $991.00 |
| Shower Mixing Valve | 1.333 | $120.00 | $65.00 | $185.00 |
| Shower Door | 1.000 | $225.00 | $48.50 | $273.50 |
| Rough-In Waste ( 1 1/2" Diameter Drain Waste Vent Piping) | 5.408 | $144.00 | $236.40 | $380.40 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 2.963 | $112.80 | $144.00 | $256.80 |
| Bathtub (P.E. Cast Iron, 5' Long with Fittings, White) | 3.636 | $830.00 | $159.00 | $989.00 |
| Rough-In Waste ( 4" Diameter Drain Waste Vent Piping) | 1.103 | $42.60 | $48.20 | $90.80 |
| Rough-In Supply ( 1/2" Diameter Type "L" Copper Piping) | 0.988 | $37.60 | $48.00 | $85.60 |
| Rough-In Vent ( 1 1/2" Diameter Drain Waste Vent Piping) | 0.593 | $50.80 | $28.80 | $79.60 |
| Piping (Supply, 1/2" Diameter Type "L" Copper Piping) | 4.148 | $157.92 | $201.60 | $359.52 |
| Waste ( 4" Diameter Drain Waste Vent Piping) | 2.759 | $106.50 | $120.50 | $227.00 |
| Vent ( 2" Diameter Drain Waste Vent Piping) | 3.250 | $121.55 | $142.35 | $263.90 |
| Vanity Base Cabinet ( 2 Door, 30" Wide) | 1.400 | $395.00 | $61.00 | $456.00 |
| Vanity Top (Plastic & Laminated, Square Edge) | 1.112 | $110.51 | $48.58 | $159.09 |
| TOTAL | 44.347 | $4,770.59 | $1,996.68 | $6,767.27 |
Gas Fired Heating/Cooling:
The costs in these systems are based on complete systems basis for one zone 1,200 S.F. buildings. For larger buildings use the price sheet on page 251 in Means Residential Square Foot Costs, Contractor Pricing Guide 2007.
| System Description | Labor Hours | Cost Per System Materials | Cost Per System Installation | Total |
|---|---|---|---|---|
| Heating Only, Gas Fired Hot Air |
| |||
| Furnace (Gas, Up Flow) | 5.000 | $745.00 | $218.00 | $963.00 |
| Intermittent Pilot |
| $151.00 | $151.00 | |
| Supply Duct (Rigid Fiberglass) | 12.068 | $119.68 | $543.84 | $663.52 |
| Return Duct (Sheet Metal, Galvanized) | 16.137 | $165.90 | $728.38 | $894.28 |
| Lateral Ducts (6" Flexible Fiberglass) | 8.862 | $401.76 | $385.92 | $787.68 |
| Register Elbows | 3.200 | $456.00 | $139.20 | $595.20 |
| Floor Registers (Enameled Steel) | 3.000 | $264.00 | $145.20 | $409.20 |
| Floor Grille (Return Air) | 0.727 | $56.00 | $35.20 | $91.20 |
| Thermostat | 1.000 | $29.50 | $48.50 | $78.00 |
| Plenum | 1.000 | $77.00 | $43.50 | $120.50 |
| TOTAL | 50.994 | $2,465.84 | $2,287.74 | $4,753.58 |
| Heating/Cooling, Gas Fired Forced Air |
| |||
| Furnace (Including Plenum, Compressor, Coil) | 14.720 | $4,347.00 | $639.40 | $4,986.40 |
| Intermittent Pilot |
| $151.00 | $151.00 | |
| Supply Duct (Rigid Fiberglass) | 12.068 | $119.68 | $543.84 | $663.52 |
| Return Duct (Sheet Metal, Galvanized) | 16.137 | $165.90 | $728.38 | $894.28 |
| Lateral Ducts (6" Flexible Fiberglass) | 8.862 | $401.76 | $385.92 | $787.68 |
| Register Elbows | 3.200 | $456.00 | $139.20 | $595.20 |
| Floor Registers (Enameled Steel) | 3.000 | $264.00 | $145.20 | $409.20 |
| Floor Grille (Return Air) | 0.727 | $56.00 | $35.20 | $91.20 |
| Thermostat | 1.000 | $29.50 | $48.50 | $78.00 |
| Refrigeration Piping ( 25 ft. Pre-charged) |
| $224.00 | $224.00 | |
| TOTAL | 59.714 | $6,214.84 | $2,665.64 | $8,880.48 |
Oil Fired Heating/Cooling:
Reserved.
Hot Water Heating:Reserved.
Rooftop Heating/Cooling:Reserved.
Division 9 - Electrical
Electric Service:A common electric service system includes a panel board (including breakers), ground cable with rod and clamp, meter socket, service entrance cable and weather cap. The more common systems are for a 100, 200 and 400 AMP service.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| 100 AMP Service |
|
|
|
|
| Weather Cap | 0.667 | $ 13.40 | $ 32.00 | $ 45.40 |
| Service Entrance Cable | 0.762 | $ 59.00 | $ 36.50 | $ 95.50 |
| Meter Socket | 2.500 | $ 41.00 | $ 120.00 | $ 161.00 |
| Ground Rod with Clamp | 1.455 | $ 15.45 | $ 69.50 | $ 84.95 |
| Ground Cable | 0.250 | $ 9.65 | $ 12.00 | $ 21.65 |
| Panel Board (12 Circuit) | 6.667 | $ 249.00 | $ 320.00 | $ 569.00 |
| TOTAL | 12.301 | $ 387.50 | $ 590.00 | $ 977.50 |
| 200 AMP Service |
|
|
|
|
| Weather Cap | 1.000 | $ 37.00 | $ 48.00 | $ 85.00 |
| Service Entrance Cable | 1.143 | $ 69.00 | $ 54.50 | $ 123.50 |
| Meter Socket | 4.211 | $ 61.50 | $ 202.00 | $ 263.50 |
| Ground Rod with Clamp | 1.818 | $ 35.50 | $ 87.00 | $ 122.50 |
| Ground Cable | 0.500 | $ 19.30 | $ 24.00 | $ 43.30 |
| 3/4" EMT | 0.308 | $ 5.45 | $ 14.75 | $ 20.20 |
| Panel Board (24 Circuit) | 12.308 | $ 570.00 | $ 490.00 | $ 1,060.00 |
| TOTAL | 21.288 | $ 797.75 | $ 920.25 | $ 1,633.00 |
| 400 AMP Service |
|
|
|
|
| Weather Cap | 2.963 | $ 395.00 | $ 142.00 | $ 537.00 |
| Service Entrance Cable | 5.760 | $ 824.40 | $ 275.40 | $ 1,099.80 |
| Meter Socket | 4.211 | $ 61.50 | $ 202.00 | $ 263.50 |
| Ground Rod with Clamp | 2.000 | $ 95.50 | $ 96.00 | $ 191.50 |
| 3/4" Greenfield | 0.485 | $ 58.60 | $ 23.20 | $ 81.80 |
| Current Transformer Cabinet | 1.000 | $ 11.20 | $ 48.00 | $ 59.20 |
| Ground Cable | 6.154 | $ 193.00 | $ 295.00 | $ 488.00 |
| Panel Board (42 Circuit) | 33.333 | $ 2,925.00 | $ 1,600.00 | $ 4,525.00 |
| TOTAL | 55.906 | $ 4,564.20 | $ 2,681.60 | $ 5,609.00 |
Electric Heating:
Reserved.
| System Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Air Conditioning Receptacles Using Non-metallic Sheathed Cable | 0.800 | $25.50 | $38.50 | $64.00 |
| Using BX Cable | 0.964 | $36.50 | $46.00 | $82.50 |
| Using EMT Conduit | 1.194 | $48.00 | $57.00 | $105.00 |
| Disposal Wiring Using Non-metallic Sheathed Cable | 0.889 | $21.50 | $42.50 | $64.00 |
| Using BX Cable | 1.067 | $31.00 | $51.00 | $82.00 |
| Using EMT Conduit | 1.333 | $45.00 | $64.00 | $109.00 |
| Dryer Circuit Using Non-metallic Sheathed Cable | 1.455 | $60.00 | $69.50 | $129.50 |
| Using BX Cable | 1.739 | $57.00 | $83.50 | $140.50 |
| Using EMT Conduit | 2.162 | $63.00 | $104.00 | $167.00 |
| Duplex Receptacles Using Non-metallic Sheathed Cable | 0.615 | $25.50 | $29.50 | $55.00 |
| Using BX Cable | 0.741 | $36.50 | $35.50 | $72.00 |
| Using EMT Conduit | 0.920 | $48.00 | $44.00 | $92.00 |
| Exhaust Fan Wiring Using Non-metallic Sheathed Cable | 0.800 | $23.00 | $38.50 | $61.50 |
| Using BX Cable | 0.964 | $34.50 | $46.00 | $80.50 |
| Using EMT Conduit | 1.194 | $45.50 | $57.00 | $102.50 |
| Furnace Circuit & Switch Using Non-metallic Sheathed Cable | 1.333 | $26.50 | $64.00 | $90.50 |
| Using BX Cable | 1.600 | $42.00 | $76.50 | $118.50 |
| Using EMT Conduit | 2.000 | $48.50 | $96.00 | $144.50 |
| Ground Fault Using Non-metallic Sheathed Cable | 1.000 | $56.00 | $48.00 | $104.00 |
| Using BX Cable | 1.212 | $64.50 | $58.00 | $122.50 |
| Using EMT Conduit | 1.481 | $84.00 | $71.00 | $155.00 |
| Heater Circuits Using Non-metallic Sheathed Cable | 1.000 | $29.50 | $48.00 | $77.50 |
| Using BX Cable | 1.212 | $34.50 | $58.00 | $92.50 |
| Using EMT Conduit | 1.481 | $45.00 | $71.00 | $116.00 |
| Lighting Wiring Using Non-metallic Sheathed Cable | 0.500 | $30.00 | $24.00 | $54.00 |
| Using BX Cable | 0.602 | $35.50 | $29.00 | $64.50 |
| Using EMT Conduit | 0.748 | $43.50 | $36.00 | $79.50 |
| Range Circuits Using Non-metallic Sheathed Cable | 2.000 | $103.00 | $96.00 | $199.00 |
| Using BX Cable | 2.424 | $137.00 | $116.00 | $253.00 |
| Using EMT Conduit | 2.963 | $102.00 | $142.00 | $244.00 |
| Switches (Single Pole) Using Non-metallic Sheathed Cable | 0.500 | $23.00 | $24.00 | $47.00 |
| Using BX Cable | 0.602 | $34.50 | $29.00 | $63.50 |
| Using EMT Conduit | 0.748 | $45.50 | $36.00 | $81.50 |
| Switches ( 3-Way) Using Non-metallic Sheathed Cable | 0.667 | $31.00 | $32.00 | $63.00 |
| Using BX Cable | 0.800 | $38.00 | $38.50 | $76.50 |
| Using EMT Conduit | 1.333 | $56.00 | $64.00 | $120.00 |
| Water Heater Using Non-metallic Sheathed Cable | 1.600 | $36.50 | $76.50 | $113.00 |
| Using BX Cable | 1.905 | $53.00 | $91.00 | $144.00 |
| Using EMT Conduit | 2.353 | $50.50 | $113.00 | $163.50 |
| Weatherproof Receptacle Using Non-metallic Sheathed Cable | 1.333 | $141.00 | $64.00 | $205.00 |
| Using BX Cable | 1.600 | $146.00 | $76.50 | $222.50 |
| Using EMT Conduit | 2.000 | $158.00 | $96.00 | $254.00 |
| Description | Labor Hours | Cost Each Materials | Cost Each Installation | Total |
|---|---|---|---|---|
| Fluorescent Strip, 4' Long, 1 Light, Average | 0.941 | $32.50 | $45.00 | $77.50 |
| Deluxe | 1.129 | $39.00 | $54.00 | $93.00 |
| 2 Light, Average | 1.000 | $35.00 | $48.00 | $83.00 |
| Deluxe | 1.200 | $42.00 | $57.50 | $99.50 |
| 8' Long, 1 Light, Average | 1.194 | $48.50 | $57.00 | $105.50 |
| Deluxe | 1.433 | $58.00 | $68.50 | $126.50 |
| 2 Light, Average | 1.290 | $58.50 | $62.00 | $120.50 |
| Deluxe | 1.548 | $70.00 | $74.50 | $144.50 |
| Surface Mounted, 4' x 1', Economy | 0.914 | $65.00 | $43.50 | $108.50 |
| Average | 1.143 | $81.00 | $54.50 | $135.50 |
| Deluxe | 1.371 | $97.00 | $65.50 | $162.50 |
| 4' x 2', Economy | 1.208 | $82.50 | $58.00 | $140.50 |
| Average | 1.509 | $103.00 | $72.50 | $175.50 |
| Deluxe | 1.811 | $124.00 | $87.00 | $211.00 |
| Recessed, 4' x 1', 2 Lamps, Economy | 1.123 | $44.50 | $53.50 | $98.00 |
| Average | 1.404 | $55.50 | $67.00 | $122.50 |
| Deluxe | 1.684 | $66.50 | $80.50 | $147.00 |
| 4' x 2', 4 Lamps, Economy | 1.362 | $53.50 | $65.00 | $118.50 |
| Average | 1.702 | $67.00 | $81.50 | $148.50 |
| Deluxe | 2.043 | $80.50 | $98.00 | $178.50 |
| Incandescent, Exterior, 150W, Single Spot | 0.500 | $21.50 | $24.00 | $45.50 |
| Double Spot | 1.167 | $81.00 | $56.00 | $137.00 |
| Recessed, 100W, Economy | 0.800 | $55.00 | $38.50 | $93.50 |
| Average | 1.000 | $69.00 | $48.00 | $117.00 |
| Deluxe | 1.200 | $83.00 | $57.50 | $140.50 |
| 150W, Economy | 0.800 | $81.50 | $38.50 | $120.00 |
| Average | 1.000 | $102.00 | $48.00 | $150.00 |
| Deluxe | 1.200 | $122.00 | $57.50 | $179.50 |
| Surfaced Mounted, 60W, Economy | 0.800 | $44.00 | $38.50 | $82.50 |
| Average | 1.000 | $49.00 | $48.00 | $97.00 |
| Deluxe | 1.194 | $66.00 | $57.00 | $123.00 |
| Metal Halide, Recessed 2' x 2', 250W | 2.500 | $335.00 | $120.00 | $455.00 |
| 2' x 2', 400W | 2.759 | $375.00 | $132.00 | $507.00 |
| Surfaced Mounted, 2' x 2', 250W | 2.963 | $340.00 | $142.00 | $482.00 |
| 2' x 2', 400W | 3.333 | $400.00 | $160.00 | $560.00 |
| High Bay, Single Unit, 400W | 3.478 | $405.00 | $167.00 | $572.00 |
| Twin Unit, 400W | 5.000 | $810.00 | $240.00 | $1,050.00 |
Division 10 - Installing Contractor's Overhead & Profit
Below are the average installing contractor's percentage markups applied to base labor rated to arrive at typical billing rates.
Column A:Labor rates are based on average open shop wages for 7 major U.S. regions. Base rates, including fringe benefits, are listed hourly and daily. These figures are the sum of the wage rated and employer-paid fringe benefits such as vacation pay and employer-paid health costs.
Column B:Workers' Compensation rates are the national average of state rates established for each trade.
Column C:Average fixed overhead figures for all trades. Included are Federal and State Unemployment costs set at 6.2%; Social Security Taxes (FICA) set at 7.65%; Builder's Risk Insurance costs set at 0.44%; and Public Liability costs set at 2.02%. All the percentages, except those for Social Security Taxes, vary from state to state as well as from company to company.
Column D and E:Percentages are based on the presumption that the installing contractor has annual billing of $2,000,000 and up. Overhead percentages may increase with smaller annual billing. The overhead percentages for any given contractor may vary greatly and depend on a number of factors such as the contractor's annual volume, engineering and logistical support costs, and staff requirements. The figures for overhead and profit will vary depending on the type of job, the job location, and the prevailing economic conditions. All factors should be examined very carefully for each job.
Column F:Lists the total of Columns B, C, D and E.
Column G:Column A (hourly base labor rate) multiplied by the percentage in
Column F:(O&P percentage).
Column H:The total of Column A (hourly base labor rate) plus Column G (Total O&P).
Column I:Column H multiplied by eight hours.
To adjust these costs to a specific location, simply multiply the cost by the factor for that city. State and postal zip code numbers arrange the data alphabetically. For a city not listed, use the factor for a nearby city with similar economic characteristics. Refer to Location Factors section of this chapter.
| Number | Trade Construction Worker Classification Titles |
|---|---|
| 1 | Asbestos/Insulation/Pipe Coverers |
| 2 | Boilermakers |
| 3 | Bricklayers |
| 4 | Bricklayer Helpers |
| 5 | Carpenters |
| 6 | Cement Finishers |
| 7 | Common Laborers |
| 8 | Electricians |
| 9 | Elevator Constructors |
| 10 | Equipment Operators Crane or Shovel |
| 11 | Equipment Operators Medium Equipment |
| 12 | Equipment Operators Light Equipment |
| 13 | Equipment Operators Oilers |
| 14 | Equipment Operators Master Mechanic |
| 15 | Foreman Inside |
| 16 | Foreman Outside |
| 17 | Glazers |
| 18 | Helpers |
| 19 | Lathers |
| 20 | Marble Setters |
| 21 | Millwrights |
| 22 | Mosaic & Terrazzo Workers |
| 23 | Painters Ordinary |
| 24 | Painters Structural Steel |
| 25 | Paper Hangers |
| 26 | Pile Drivers |
| 27 | Plasterers |
| 28 | Plasterer Helpers |
| 29 | Plumbers |
| 30 | Rodmen Reinforcing |
| 31 | Roofers Composition |
| 32 | Roofers Tile & Slate |
| 33 | Roofers Helpers Composition |
| 34 | Sheet Metal Workers |
| 35 | Skilled Workers |
| 36 | Sprinkler Installers |
| 37 | Steamfitters or Pipefitters |
| 38 | Stone Masons |
| 39 | Structural Steel Workers |
| 40 | Tile Layers |
| 41 | Tile Layers Helpers |
| 42 | Truck Drivers Light |
| 43 | Truck Drivers Heavy |
| 44 | Welders Structural Steel |
| 45 | Wrecking (Not Included In Averages) |
| # | A Hourly Base Rate Incl. Fringes | A Daily Base Rate Incl. Fringes | B Workers' Comp. Ins. | C Average Fixed Overhead | D Overhead | E Profit | F Total Overhead & Profit % | G Total Overhead & Profit Amount | H Hourly Rates With Overhead & Profit | I Daily Rates With Overhead & Profit |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | $27.40 | $219.20 | 15.8% | 16.3% | 30.0% | 10.0% | 72.1% | $19.75 | $47.15 | $377.20 |
| 2 | $31.10 | $248.80 | 12.7% | 16.3% | 30.0% | 10.0% | 69.0% | $21.45 | $52.55 | $420.40 |
| 3 | $26.65 | $213.20 | 14.9% | 16.3% | 25.0% | 10.0% | 66.2% | $17.65 | $44.30 | $354.40 |
| 4 | $20.05 | $160.40 | 14.9% | 16.3% | 25.0% | 10.0% | 66.2% | $13.25 | $33.30 | $266.40 |
| 5 | $25.70 | $205.60 | 18.4% | 16.3% | 25.0% | 10.0% | 69.7% | $17.90 | $43.60 | $348.80 |
| 6 | $24.90 | $199.20 | 9.6% | 16.3% | 25.0% | 10.0% | 60.9% | $15.15 | $40.05 | $320.40 |
| 7 | $18.70 | $149.60 | 18.4% | 16.3% | 25.0% | 10.0% | 69.7% | $13.05 | $31.75 | $254.00 |
| 8 | $29.40 | $235.20 | 6.6% | 16.3% | 30.0% | 10.0% | 62.9% | $18.50 | $47.90 | $383.20 |
| 9 | $35.80 | $286.40 | 6.9% | 16.3% | 30.0% | 10.0% | 63.2% | $22.65 | $58.45 | $467.60 |
| 10 | $27.45 | $219.60 | 10.4% | 16.3% | 28.0% | 10.0% | 64.7% | $17.75 | $45.20 | $361.60 |
| 11 | $26.50 | $212.00 | 10.4% | 16.3% | 28.0% | 10.0% | 64.7% | $17.15 | $43.65 | $349.20 |
| 12 | $25.45 | $203.60 | 10.4% | 16.3% | 28.0% | 10.0% | 64.7% | $16.45 | $41.90 | $335.20 |
| 13 | $23.40 | $187.20 | 10.4% | 16.3% | 28.0% | 10.0% | 64.7% | $15.15 | $38.55 | $308.40 |
| 14 | $27.65 | $221.20 | 10.4% | 16.3% | 28.0% | 10.0% | 64.7% | $17.90 | $45.55 | $364.40 |
| 15 | $26.60 | $212.80 | 16.3% | 16.3% | 27.0% | 10.0% | 69.6% | $18.50 | $45.10 | $360.80 |
| 16 | $28.10 | $224.80 | 16.3% | 16.3% | 27.0% | 10.0% | 69.6% | $19.55 | $47.65 | $381.20 |
| 17 | $25.60 | $204.80 | 14.1% | 16.3% | 25.0% | 10.0% | 65.4% | $16.75 | $42.35 | $338.80 |
| 18 | $18.80 | $150.40 | 17.8% | 16.3% | 25.0% | 10.0% | 69.1% | $13.00 | $31.80 | $254.00 |
| 19 | $23.60 | $188.80 | 11.6% | 16.3% | 25.0% | 10.0% | 62.9% | $14.85 | $38.45 | $307.60 |
| 20 | $25.35 | $202.80 | 14.9% | 16.3% | 25.0% | 10.0% | 66.2% | $16.80 | $42.15 | $337.20 |
| 21 | $26.75 | $214.00 | 10.2% | 16.3% | 25.0% | 10.0% | 61.5% | $16.45 | $43.20 | $345.60 |
| 22 | $24.60 | $196.80 | 9.5% | 16.3% | 25.0% | 10.0% | 60.8% | $14.95 | $39.55 | $316.40 |
| 23 | $23.20 | $185.60 | 13.2% | 16.3% | 25.0% | 10.0% | 64.5% | $14.95 | $38.15 | $305.20 |
| 24 | $23.80 | $190.40 | 45.3% | 16.3% | 25.0% | 10.0% | 96.6% | $23.00 | $46.80 | $374.40 |
| 25 | $23.35 | $186.80 | 13.2% | 16.3% | 25.0% | 10.0% | 64.5% | $15.05 | $38.40 | $307.20 |
| 26 | $25.15 | $201.20 | 21.4% | 16.3% | 30.0% | 10.0% | 77.7% | $19.55 | $44.70 | $357.60 |
| 27 | $23.50 | $188.00 | 14.0% | 16.3% | 25.0% | 10.0% | 65.3% | $12.35 | $38.85 | $310.80 |
| 28 | $20.15 | $161.20 | 14.0% | 16.3% | 25.0% | 10.0% | 65.3% | $13.15 | $33.30 | $266.40 |
| 29 | $29.55 | $236.40 | 8.1% | 16.3% | 30.0% | 10.0% | 64.4% | $19.05 | $48.60 | $388.80 |
| 30 | $27.65 | $221.20 | 23.8% | 16.3% | 28.0% | 10.0% | 78.1% | $21.60 | $49.25 | $394.00 |
| 31 | $21.95 | $175.60 | 32.3% | 16.3% | 25.0% | 10.0% | 83.6% | $18.35 | $40.30 | $322.40 |
| 32 | $22.05 | $176.40 | 32.3% | 16.3% | 25.0% | 10.0% | 83.6% | $18.45 | $40.50 | $324.00 |
| 33 | $16.10 | $128.80 | 32.3% | 16.3% | 25.0% | 10.0% | 83.6% | $13.45 | $29.55 | $236.40 |
| 34 | $28.75 | $230.00 | 11.9% | 16.3% | 30.0% | 10.0% | 68.2% | $19.60 | $48.35 | $386.80 |
| 35 | $26.10 | $208.80 | 16.3% | 16.3% | 27.0% | 10.0% | 69.6% | $18.15 | $44.25 | $354.00 |
| 36 | $29.25 | $234.00 | 8.3% | 16.3% | 30.0% | 10.0% | 64.6% | $18.90 | $48.15 | $385.20 |
| 37 | $29.85 | $238.80 | 8.1% | 16.3% | 30.0% | 10.0% | 64.4% | $19.20 | $49.05 | $392.40 |
| 38 | $26.05 | $208.40 | 14.9% | 16.3% | 25.0% | 10.0% | 66.2% | $17.25 | $43.30 | $346.40 |
| 39 | $27.70 | $221.60 | 40.8% | 16.3% | 28.0% | 10.0% | 95.1% | $26.35 | $54.05 | $432.40 |
| 40 | $24.85 | $198.80 | 9.5% | 16.3% | 25.0% | 10.0% | 60.8% | $15.10 | $39.95 | $319.60 |
| 41 | $19.10 | $152.80 | 9.5% | 16.3% | 25.0% | 10.0% | 60.8% | $11.60 | $30.70 | $245.60 |
| 42 | $20.25 | $162.00 | 17.1% | 16.3% | 25.0% | 10.0% | 68.4% | $13.85 | $34.10 | $272.80 |
| 43 | $21.00 | $168.00 | 17.1% | 16.3% | 25.0% | 10.0% | 68.4% | $14.35 | $35.35 | $282.80 |
| 44 | $27.70 | $221.60 | 40.8% | 16.3% | 28.0% | 10.0% | 95.1% | $26.35 | $54.05 | $432.40 |
| 45 | $19.25 | $154.00 | 39.1% | 16.3% | 25.0% | 10.0% | 90.4% | $17.40 | $36.65 | $293.20 |
Location Factors
Costs shown in RSMeans Cost Data Publications are based on National Averages for materials and installation. To adjust these costs to a specific location, simply multiply the base cost by the factor for that city. State and postal zip code numbers arrange the data alphabetically. For a city not listed, use the factor for a nearby city with similar economic characteristics.
| State | Zip Code | City | Factor |
|---|---|---|---|
| Alabama | 350-352 | Birmingham | 0.86 |
| Alabama | 354 | Tuscaloosa | 0.73 |
| Alabama | 355 | Jasper | 0.71 |
| Alabama | 356 | Decatur | 0.76 |
| Alabama | 357-358 | Huntsville | 0.84 |
| Alabama | 359 | Gadsden | 0.73 |
| Alabama | 360-361 | Montgomery | 0.75 |
| Alabama | 362 | Anniston | 0.68 |
| Alabama | 363 | Dothan | 0.74 |
| Alabama | 364 | Evergreen | 0.70 |
| Alabama | 365-366 | Mobile | 0.79 |
| Alabama | 367 | Selma | 0.72 |
| Alabama | 368 | Phenix City | 0.73 |
| Alabama | 369 | Butler | 0.71 |
| Alaska | 995-996 | Anchorage | 1.27 |
| Alaska | 997 | Fairbanks | 1.29 |
| Alaska | 998 | Juneau | 1.27 |
| Alaska | 999 | Ketchikan | 1.29 |
| Arizona | 850-853 | Phoenix | 0.86 |
| Arizona | 852 | Mesa/Tempe | 0.83 |
| Arizona | 855 | Globe | 0.79 |
| Arizona | 856-857 | Tucson | 0.84 |
| Arizona | 859 | Show Low | 0.81 |
| Arizona | 860 | Flagstaff | 0.86 |
| Arizona | 863 | Prescott | 0.81 |
| Arizona | 864 | Kingman | 0.83 |
| Arizona | 865 | Chambers | 0.80 |
| Arkansas | 716 | Pine Bluff | 0.81 |
| Arkansas | 717 | Camden | 0.70 |
| Arkansas | 718 | Texarkana | 0.75 |
| Arkansas | 719 | Hot Springs | 0.70 |
| Arkansas | 720-722 | Little Rock | 0.87 |
| Arkansas | 723 | West Memphis | 0.81 |
| Arkansas | 724 | Jonesboro | 0.79 |
| Arkansas | 725 | Batesville | 0.76 |
| Arkansas | 726 | Harrison | 0.78 |
| Arkansas | 727 | Fayetteville | 0.72 |
| Arkansas | 728 | Russellville | 0.77 |
| Arkansas | 729 | Fort Smith | 0.79 |
| California | 900-902 | Los Angeles | 1.06 |
| California | 903-905 | Inglewood | 1.05 |
| California | 906-908 | Long Beach | 1.04 |
| California | 910-912 | Pasadena | 1.05 |
| California | 913-916 | Van Nuys | 1.08 |
| California | 917-917 | Alhambra | 1.09 |
| California | 919-921 | San Diego | 1.04 |
| California | 922 | Palm Springs | 1.04 |
| California | 923-924 | San Bernardino | 1.05 |
| California | 925 | Riverside | 1.05 |
| California | 926-927 | Santa Ana | 1.06 |
| California | 928 | Anaheim | 1.05 |
| California | 930 | Oxnard | 1.07 |
| California | 931 | Santa Barbara | 1.06 |
| California | 932-933 | Bakersfield | 1.03 |
| California | 934 | San Luis Obispo | 1.08 |
| California | 935 | Mojave | 1.06 |
| California | 936-938 | Fresno | 1.09 |
| California | 939 | Salinas | 1.12 |
| California | 940-941 | San Francisco | 1.23 |
| California | 942,956-958 | Sacramento | 1.11 |
| California | 943 | Palo Alto | 1.18 |
| California | 944 | San Mateo | 1.22 |
| California | 945 | Vallejo | 1.15 |
| California | 946 | Oakland | 1.21 |
| California | 947 | Berkeley | 1.24 |
| California | 948 | Richmond | 1.24 |
| California | 949 | San Rafael | 1.22 |
| California | 950 | Santa Cruz | 1.15 |
| California | 951 | San Jose | 1.19 |
| California | 952 | Stockton | 1.09 |
| California | 953 | Modesto | 1.08 |
| California | 954 | Santa Rosa | 1.16 |
| California | 955 | Eureka | 1.12 |
| California | 959 | Marysville | 1.10 |
| California | 960 | Redding | 1.10 |
| California | 961 | Susanville | 1.09 |
| Colorado | 800-802 | Denver | 0.94 |
| Colorado | 803 | Boulder | 0.93 |
| Colorado | 804 | Golden | 0.91 |
| Colorado | 805 | Fort Collins | 0.9 |
| Colorado | 806 | Greeley | 0.80 |
| Colorado | 807 | Fort Morgan | 0.93 |
| Colorado | 808-809 | Colorado Springs | 0.90 |
| Colorado | 810 | Pueblo | 0.91 |
| Colorado | 811 | Alamosa | 0.88 |
| Colorado | 812 | Salida | 0.90 |
| Colorado | 813 | Durango | 0.91 |
| Colorado | 814 | Montrose | 0.87 |
| Colorado | 815 | Grand Junction | 0.92 |
| Colorado | 816 | Glenwood Springs | 0.90 |
| Connecticut | 060 | New Britain | 1.08 |
| Connecticut | 061 | Hartford | 1.08 |
| Connecticut | 062 | Willimantic | 1.08 |
| Connecticut | 063 | New London | 1.08 |
| Connecticut | 064 | Meriden | 1.08 |
| Connecticut | 065 | New Haven | 1.08 |
| Connecticut | 066 | Bridgeport | 1.09 |
| Connecticut | 067 | Waterbury | 1.09 |
| Connecticut | 068 | Norwalk | 1.09 |
| Connecticut | 069 | Stanford | 1.10 |
| District of Columbia | 200-205 | Washington | 0.95 |
| Delaware | 197 | Newark | 0.99 |
| Delaware | 198 | Wilmington | 1.00 |
| Delaware | 199 | Dover | 0.99 |
| Florida | 320-322 | Jacksonville | 0.77 |
| Florida | 321 | Daytona Beach | 0.84 |
| Florida | 323 | Tallahassee | 0.73 |
| Florida | 324 | Panama City | 0.67 |
| Florida | 325 | Pensacola | 0.78 |
| Florida | 326-344 | Gainesville | 0.77 |
| Florida | 327-328,347 | Orlando | 0.84 |
| Florida | 329 | Melbourne | 0.86 |
| Florida | 330-332,340 | Miami | 0.85 |
| Florida | 333 | Fort Lauderdale | 0.84 |
| Florida | 334,349 | West Palm Beach | 0.84 |
| Florida | 335-336,346 | Tampa | 0.86 |
| Florida | 337 | St Petersburg | 0.76 |
| Florida | 338 | Lakeland | 0.83 |
| Florida | 339,341 | Fort Myers | 0.80 |
| Florida | 342 | Sarasota | 0.84 |
| Georgia | 300-303,399 | Atlanta | 0.90 |
| Georgia | 304 | Statesboro | 0.71 |
| Georgia | 305 | Gainesville | 0.79 |
| Georgia | 306 | Athens | 0.79 |
| Georgia | 307 | Dalton | 0.75 |
| Georgia | 308-309 | Augusta | 0.81 |
| Georgia | 310-312 | Macon | 0.82 |
| Georgia | 313-314 | Savannah | 0.82 |
| Georgia | 315 | Waycross | 0.76 |
| Georgia | 316 | Valdosta | 0.73 |
| Georgia | 317,398 | Albany | 0.79 |
| Georgia | 318-319 | Columbus | 0.83 |
| Hawaii | 967 | Hilo | 1.21 |
| Hawaii | 968 | Honolulu | 1.23 |
| Idaho | 832 | Pocatello | 0.86 |
| Idaho | 833 | Twin Falls | 0.74 |
| Idaho | 834 | Idaho Falls | 0.75 |
| Idaho | 835 | Lewiston | 0.96 |
| Idaho | 836-837 | Boise | 0.87 |
| Idaho | 838 | Coeur d'Alene | 0.94 |
| Illinois | 600-603 | North Suburban | 1.10 |
| Illinois | 604 | Joliet | 1.10 |
| Illinois | 605 | South Suburban | 1.10 |
| Illinois | 606-608 | Chicago | 1.16 |
| Illinois | 609 | Kankakee | 1.00 |
| Illinois | 610-611 | Rockford | 1.04 |
| Illinois | 612 | Rock Island | 0.96 |
| Illinois | 613 | La Salle | 1.02 |
| Illinois | 614 | Galesburg | 0.99 |
| Illinois | 615-616 | Peoria | 0.98 |
| Illinois | 617 | Bloomington | 0.98 |
| Illinois | 618-619 | Champaign | 0.99 |
| Illinois | 620-622 | East St Louis | 1.00 |
| Illinois | 623 | Quincy | 0.98 |
| Illinois | 624 | Effingham | 0.96 |
| Illinois | 625 | Decatur | 0.97 |
| Illinois | 626-627 | Springfield | 0.97 |
| Illinois | 628 | Centralia | 1.00 |
| Illinois | 629 | Carbondale | 0.95 |
| Indiana | 460 | Anderson | 0.91 |
| Indiana | 461-462 | Indianapolis | 0.95 |
| Indiana | 463-464 | Gary | 1.01 |
| Indiana | 465-466 | South Bend | 0.91 |
| Indiana | 467-468 | Fort Wayne | 0.91 |
| Indiana | 469 | Kokomo | 0.92 |
| Indiana | 470 | Lawrenceburg | 0.87 |
| Indiana | 471 | New Albany | 0.86 |
| Indiana | 472 | Columbus | 0.92 |
| Indiana | 473 | Muncie | 0.91 |
| Indiana | 474 | Bloomington | 0.94 |
| Indiana | 475 | Washington | 0.91 |
| Indiana | 476-477 | Evansville | 0.90 |
| Indiana | 478 | Terre Haute | 0.90 |
| Indiana | 479 | Lafayette | 0.91 |
| Iowa | 500-503,509 | Des Moines | 0.91 |
| Iowa | 504 | Mason City | 0.77 |
| Iowa | 505 | Fort Dodge | 0.76 |
| Iowa | 506-507 | Waterloo | 0.79 |
| Iowa | 508 | Creston | 0.81 |
| Iowa | 510-511 | Sioux City | 0.87 |
| Iowa | 512 | Sibley | 0.73 |
| Iowa | 513 | Spencer | 0.74 |
| Iowa | 514 | Carroll | 0.74 |
| Iowa | 515 | Council Bluffs | 0.81 |
| Iowa | 516 | Shenadoah | 0.75 |
| Iowa | 520 | Dubuque | 0.86 |
| Iowa | 521 | Decorah | 0.76 |
| Iowa | 522-524 | Cedar Rapids | 0.94 |
| Iowa | 525 | Ottumwa | 0.84 |
| Iowa | 526 | Burlington | 0.87 |
| Iowa | 527-528 | Davenport | 0.97 |
| Kansas | 660-662 | Kansas City | 0.99 |
| Kansas | 664-666 | Topeka | 0.80 |
| Kansas | 667 | Fort Scott | 0.85 |
| Kansas | 668 | Emporia | 0.72 |
| Kansas | 669 | Belleville | 0.78 |
| Kansas | 670-672 | Wichita | 0.80 |
| Kansas | 673 | Independence | 0.85 |
| Kansas | 674 | Salina | 0.76 |
| Kansas | 675 | Hutchinson | 0.77 |
| Kansas | 676 | Hays | 0.82 |
| Kansas | 677 | Colby | 0.83 |
| Kansas | 678 | Dodge City | 0.82 |
| Kansas | 679 | Liberal | 0.79 |
| Kentucky | 400-402 | Louisville | 0.92 |
| Kentucky | 403-405 | Lexington | 0.89 |
| Kentucky | 406 | Frankfort | 0.89 |
| Kentucky | 407-409 | Corbin | 0.78 |
| Kentucky | 410 | Covington | 1.00 |
| Kentucky | 411-412 | Ashland | 0.98 |
| Kentucky | 413-414 | Campton | 0.79 |
| Kentucky | 415-416 | Pikeville | 0.86 |
| Kentucky | 417-418 | Hazard | 0.73 |
| Kentucky | 420 | Paducah | 0.90 |
| Kentucky | 421-422 | Bowling Green | 0.90 |
| Kentucky | 423 | Owensboro | 0.89 |
| Kentucky | 424 | Henderson | 0.91 |
| Kentucky | 425-426 | Somerset | 0.78 |
| Kentucky | 427 | Elizabethtown | 0.87 |
| Louisiana | 700-701 | New Orleans | 0.86 |
| Louisiana | 703 | Thibodaux | 0.84 |
| Louisiana | 704 | Hammond | 0.79 |
| Louisiana | 705 | Lafayette | 0.82 |
| Louisiana | 706 | Lake Charles | 0.83 |
| Louisiana | 707-708 | Baton Rouge | 0.82 |
| Louisiana | 710-711 | Shreveport | 0.79 |
| Louisiana | 712 | Monroe | 0.74 |
| Louisiana | 713-714 | Alexandria | 0.74 |
| Maine | 039 | Kittery | 0.79 |
| 040-041 | Portland | 0.90 | |
| Maine | 042 | Lewiston | 0.89 |
| Maine | 043 | Augusta | 0.82 |
| Maine | 044 | Bangor | 0.88 |
| Maine | 045 | Bath | 0.80 |
| Maine | 046 | Machias | 0.81 |
| Maine | 047 | Houlton | 0.85 |
| Maine | 048 | Rockland | 0.81 |
| Maine | 049 | Waterville | 0.80 |
| Maryland | 203 | Waldorf | 0.85 |
| Maryland | 207-208 | College Park | 0.87 |
| Maryland | 209 | Silver Spring | 0.86 |
| Maryland | 210-212 | Baltimore | 0.90 |
| Maryland | 214 | Annapolis | 0.85 |
| Maryland | 215 | Cumberland | 0.86 |
| Maryland | 216 | Easton | 0.68 |
| Maryland | 217 | Hagerstown | 0.86 |
| Maryland | 218 | Salisbury | 0.75 |
| Maryland | 219 | Elkton | 0.81 |
| Maryland | 203 | Waldorf | 0.85 |
| Maryland | 207-208 | College Park | 0.87 |
| Maryland | 209 | Silver Spring | 0.86 |
| Maryland | 210-212 | Baltimore | 0.90 |
| Maryland | 214 | Annapolis | 0.85 |
| Maryland | 215 | Cumberland | 0.86 |
| Maryland | 216 | Easton | 0.68 |
| Maryland | 217 | Hagerstown | 0.86 |
| Maryland | 218 | Salisbury | 0.75 |
| Maryland | 219 | Elkton | 0.81 |
| Massachusetts | 010-011 | Springfield | 1.04 |
| Massachusetts | 012 | Pittsfield | 1.01 |
| Massachusetts | 013 | Greenfield | 1.00 |
| Massachusetts | 014 | Fitchburg | 1.12 |
| Massachusetts | 015-016 | Worcester | 1.14 |
| Massachusetts | 017 | Framingham | 1.12 |
| Massachusetts | 018 | Lowell | 1.13 |
| Massachusetts | 019 | Lawrence | 1.13 |
| Massachusetts | 020-022,024 | Boston | 1.19 |
| Massachusetts | 023 | Brockton | 1.12 |
| Massachusetts | 025 | Buzzards Bay | 1.10 |
| Massachusetts | 026 | Hyannis | 1.09 |
| Massachusetts | 027 | New Bedford | 1.12 |
| Michigan | 480-483 | Royal Oat | 1.03 |
| Michigan | 481 | Ann Arbor | 1.05 |
| Michigan | 482 | Detroit | 1.07 |
| Michigan | 484-485 | Flint | 0.97 |
| Michigan | 486 | Saginaw | 0.94 |
| Michigan | 487 | Bay City | 0.95 |
| Michigan | 488-489 | Lansing | 0.97 |
| Michigan | 490 | Battle Creek | 0.93 |
| Michigan | 491 | Kalamazoo | 0.92 |
| Michigan | 492 | Jackson | 0.95 |
| Michigan | 493,495 | Grand Rapids | 0.82 |
| Michigan | 494 | Muskegon | 0.89 |
| Michigan | 496 | Traverse City | 0.80 |
| Michigan | 497 | Gaylord | 0.83 |
| Michigan | 498-499 | Iron Mountain | 0.90 |
| Minnesota | 550-551 | Saint Paul | 1.13 |
| Minnesota | 553-555 | Minneapolis | 1.17 |
| Minnesota | 556-558 | Duluth | 1.09 |
| Minnesota | 559 | Rochester | 1.05 |
| Minnesota | 560 | Mankato | 1.03 |
| Minnesota | 561 | Windom | 0.83 |
| Minnesota | 562 | Willmar | 0.85 |
| Minnesota | 563 | St Cloud | 1.07 |
| Minnesota | 564 | Brainerd | 0.98 |
| Minnesota | 565 | Detroit Lakes | 0.96 |
| Minnesota | 566 | Bemidji | 0.96 |
| Minnesota | 567 | Their River Falls | 0.95 |
| Mississippi | 386 | Clarksdale | 0.62 |
| Mississippi | 387 | Greenville | 0.69 |
| Mississippi | 388 | Tupelo | 0.64 |
| Mississippi | 389 | Greenwood | 0.65 |
| Mississippi | 390-392 | Jackson | 0.73 |
| Mississippi | 393 | Meridian | 0.66 |
| Mississippi | 394 | Laurel | 0.63 |
| Mississippi | 395 | Biloxi | 0.75 |
| Mississippi | 396 | McComb | 0.74 |
| Mississippi | 397 | Columbus | 0.65 |
| Missouri | 630-631 | St Louis | 1.03 |
| Missouri | 633 | Bowling Green | 0.94 |
| Missouri | 634 | Hannibal | 0.87 |
| Missouri | 635 | Kirksville | 0.80 |
| Missouri | 636 | Flat River | 0.94 |
| Missouri | 637 | Cape Girardeau | 0.87 |
| Missouri | 638 | Sikeston | 0.82 |
| Missouri | 639 | Poplar Bluff | 0.82 |
| Missouri | 640-641 | Kansas City | 1.03 |
| Missouri | 644-645 | St Joseph | 0.95 |
| Missouri | 646 | Chillicothe | 0.84 |
| Missouri | 647 | Harrisonville | 0.94 |
| Missouri | 648 | Joplin | 0.85 |
| Missouri | 650-651 | Jefferson City | 0.88 |
| Missouri | 652 | Columbia | 0.88 |
| Missouri | 653 | Sedalia | 0.85 |
| Missouri | 654-655 | Rolla | 0.88 |
| Missouri | 656-658 | Springfield | 0.86 |
| Montana | 590-591 | Billings | 0.87 |
| Montana | 592 | Wolf Point | 0.83 |
| Montana | 593 | Miles City | 0.85 |
| Montana | 594 | Great Falls | 0.88 |
| Montana | 595 | Havre | 0.80 |
| Montana | 596 | Helena | 0.87 |
| Montana | 597 | Butte | 0.83 |
| Montana | 598 | Missoula | 0.83 |
| Montana | 599 | Kalispell | 0.81 |
| Nebraska | 680-681 | Omaha | 0.89 |
| Nebraska | 683-685 | Lincoln | 0.78 |
| Nebraska | 686 | Columbus | 0.70 |
| Nebraska | 687 | Norfolk | 0.77 |
| Nebraska | 688 | Grand Island | 0.77 |
| Nebraska | 689 | Hastings | 0.76 |
| Nebraska | 690 | Mccook | 0.70 |
| Nebraska | 691 | North Platte | 0.75 |
| Nebraska | 692 | Valentine | 0.66 |
| Nebraska | 693 | Alliance | 0.66 |
| Nevada | 889-891 | Las Vegas | 1.00 |
| Nevada | 893 | Ely | 0.87 |
| Nevada | 894-895 | Reno | 0.94 |
| Nevada | 897 | Carson City | 0.95 |
| Nevada | 898 | Elko | 0.93 |
| New Hampshire | 030 | Nashua | 0.95 |
| New Hampshire | 031 | Manchester | 0.95 |
| New Hampshire | 032-033 | Concord | 0.92 |
| New Hampshire | 034 | Keene | 0.72 |
| New Hampshire | 035 | Littleton | 0.80 |
| New Hampshire | 036 | Charleston | 0.70 |
| New Hampshire | 037 | Claremont | 0.71 |
| New Hampshire | 038 | Portsmouth | 0.89 |
| New Jersey | 070-071 | Newark | 1.13 |
| New Jersey | 072 | Elizabeth | 1.15 |
| New Jersey | 073 | Jersey City | 1.11 |
| New Jersey | 074-075 | Paterson | 1.12 |
| New Jersey | 076 | Hackensack | 1.11 |
| New Jersey | 077 | Long Branch | 1.13 |
| New Jersey | 078 | Dover | 1.12 |
| New Jersey | 079 | Summit | 1.12 |
| New Jersey | 080-083 | Vineland | 1.09 |
| New Jersey | 081 | Camden | 1.10 |
| New Jersey | 082-084 | Atlantic City | 1.13 |
| New Jersey | 085-086 | Trenton | 1.11 |
| New Jersey | 087 | Point Pleasant | 1.10 |
| New Jersey | 088-089 | New Brunswick | 1.12 |
| New Mexico | 870-872 | Albuquerque | 0.85 |
| New Mexico | 873 | Gallup | 0.85 |
| New Mexico | 874 | Farmington | 0.85 |
| New Mexico | 875 | Santa Fe | 0.85 |
| New Mexico | 877 | Las Vegas | 0.85 |
| New Mexico | 878 | Socorro | 0.85 |
| New Mexico | 879 | Truth or Consequences | 0.84 |
| New Mexico | 880 | Las Cruces | 0.82 |
| New Mexico | 881 | Clovis | 0.84 |
| New Mexico | 882 | Roswell | 0.85 |
| New Mexico | 883 | Carrizozo | 0.85 |
| New Mexico | 884 | Tucumcari | 0.85 |
| New York | 100-102 | New York | 1.34 |
| New York | 103 | Staten Island | 1.25 |
| New York | 104 | Bronx | 1.27 |
| New York | 105 | Mount Vernon | 1.15 |
| New York | 106 | White Plains | 1.18 |
| New York | 107 | Yonkers | 1.19 |
| New York | 108 | New Rochelle | 1.19 |
| New York | 109 | Suffern | 1.12 |
| New York | 110 | Queens | 1.26 |
| New York | 111 | Long Island City | 1.29 |
| New York | 112 | Brooklyn | 1.31 |
| New York | 113 | Flushing | 1.28 |
| New York | 114 | Jamaica | 1.28 |
| New York | 115,117,118 | Hicksville | 1.19 |
| New York | 116 | Far Rockaway | 1.27 |
| New York | 119 | Riverhead | 1.21 |
| New York | 120-122 | Albany | 0.95 |
| New York | 123 | Schenectady | 0.96 |
| New York | 124 | Kingston | 1.03 |
| New York | 125-126 | Poughkeepsie | 1.04 |
| New York | 127 | Monticello | 1.05 |
| New York | 128 | Glens Falls | 0.89 |
| New York | 129 | Plattsburgh | 0.93 |
| New York | 130-132 | Syracuse | 0.96 |
| New York | 133-135 | Utica | 0.93 |
| New York | 136 | Watertown | 0.90 |
| New York | 137-139 | Binghamton | 0.95 |
| New York | 140-142 | Buffalo | 1.05 |
| New York | 143 | Niagara Falls | 1.01 |
| New York | 144-146 | Rochester | 0.99 |
| New York | 147 | Jamestown | 0.89 |
| New York | 148-149 | Elmira | 0.86 |
| North Carolina | 270,272-274 | Greensboro | 0.85 |
| North Carolina | 271 | Winston-Salem | 0.85 |
| North Carolina | 275-276 | Raleigh | 0.87 |
| North Carolina | 277 | Durham | 0.85 |
| North Carolina | 278 | Rocky Mount | 0.75 |
| North Carolina | 279 | Elizabeth City | 0.75 |
| North Carolina | 280 | Gastonia | 0.86 |
| North Carolina | 281-282 | Charlotte | 0.88 |
| North Carolina | 283 | Fayetteville | 0.84 |
| North Carolina | 284 | Wilmington | 0.83 |
| North Carolina | 285 | Kinston | 0.75 |
| North Carolina | 286 | Hickory | 0.80 |
| North Carolina | 287-288 | Asheville | 0.83 |
| North Carolina | 289 | Murphy | 0.74 |
| North Dakota | 580-581 | Fargo | 0.79 |
| North Dakota | 582 | Grand Forks | 0.76 |
| North Dakota | 583 | Devils Lake | 0.79 |
| North Dakota | 584 | Jamestown | 0.74 |
| North Dakota | 585 | Bismarck | 0.79 |
| North Dakota | 586 | Dickinson | 0.77 |
| North Dakota | 587 | Minot | 0.80 |
| North Dakota | 588 | Williston | 0.77 |
| Ohio | 430-432 | Columbus | 0.94 |
| Ohio | 433 | Marion | 0.91 |
| Ohio | 434-436 | Toledo | 0.99 |
| Ohio | 437-438 | Zanesville | 0.90 |
| Ohio | 439 | Steubenville | 0.95 |
| Ohio | 440 | Lorain | 0.99 |
| Ohio | 441 | Cleveland | 1.02 |
| Ohio | 442-443 | Akron | 0.98 |
| Ohio | 444-445 | Youngstown | 0.96 |
| Ohio | 446-447 | Canton | 0.94 |
| Ohio | 448-449 | Mansfield | 0.95 |
| Ohio | 450 | Hamilton | 0.93 |
| Ohio | 451-452 | Cincinnati | 0.93 |
| Ohio | 453-454 | Dayton | 0.91 |
| Ohio | 455 | Springfield | 0.93 |
| Ohio | 456 | Chillicothe | 0.96 |
| Ohio | 457 | Athens | 0.88 |
| Ohio | 458 | Lima | 0.90 |
| Oklahoma | 730-731 | Oklahoma City | 0.8 |
| Oklahoma | 734 | Ardmore | 0.79 |
| Oklahoma | 735 | Lawton | 0.82 |
| Oklahoma | 736 | Clinton | 0.78 |
| Oklahoma | 737 | Enid | 0.78 |
| Oklahoma | 738 | Woodward | 0.77 |
| Oklahoma | 739 | Guymon | 0.68 |
| Oklahoma | 740-741 | Tulsa | 0.79 |
| Oklahoma | 743 | Miami | 0.82 |
| Oklahoma | 744 | Muskogee | 0.73 |
| Oklahoma | 745 | McAlester | 0.74 |
| Oklahoma | 746 | Ponca City | 0.78 |
| Oklahoma | 747 | Durant | 0.77 |
| Oklahoma | 748 | Shawnee | 0.76 |
| Oklahoma | 749 | Poteau | 0.78 |
| Oregon | 970-972 | Portland | 1.02 |
| Oregon | 973 | Salem | 1.01 |
| Oregon | 974 | Eugene | 1.01 |
| Oregon | 975 | Medford | 0.99 |
| Oregon | 976 | Klamath Falls | 1.00 |
| Oregon | 977 | Bend | 1.02 |
| Oregon | 978 | Pendleton | 0.99 |
| Oregon | 979 | Vale | 0.98 |
| Pennsylvania | 150-152 | Pittsburgh | 0.99 |
| Pennsylvania | 153 | Washington | 0.94 |
| Pennsylvania | 154 | Uniontown | 0.90 |
| Pennsylvania | 155 | Bedford | 0.88 |
| Pennsylvania | 156 | Greensburg | 0.94 |
| Pennsylvania | 157 | Indiana | 0.91 |
| Pennsylvania | 158 | Dubois | 0.90 |
| Pennsylvania | 159 | Johnstown | 0.89 |
| Pennsylvania | 160 | Butler | 0.92 |
| Pennsylvania | 161 | New Castle | 0.92 |
| Pennsylvania | 162 | Kittanning | 0.93 |
| Pennsylvania | 163 | Oil City | 0.90 |
| Pennsylvania | 164-165 | Erie | 0.95 |
| Pennsylvania | 166 | Altoona | 0.88 |
| Pennsylvania | 167 | Bradford | 0.90 |
| Pennsylvania | 168 | State College | 0.91 |
| Pennsylvania | 169 | Wellsboro | 0.90 |
| Pennsylvania | 170-171 | Harrisburg | 0.94 |
| Pennsylvania | 172 | Chambersburg | 0.89 |
| Pennsylvania | 173-174 | York | 0.91 |
| Pennsylvania | 175-176 | Lancaster | 0.91 |
| Pennsylvania | 177 | Williamsport | 0.84 |
| Pennsylvania | 178 | Sunbury | 0.91 |
| Pennsylvania | 179 | Pottsville | 0.91 |
| Pennsylvania | 180 | Lehigh Valley | 1.01 |
| Pennsylvania | 181 | Allentown | 1.04 |
| Pennsylvania | 182 | Hazleton | 0.91 |
| Pennsylvania | 183 | Stroudsburg | 0.92 |
| Pennsylvania | 184-185 | Scranton | 0.96 |
| Pennsylvania | 186-187 | Wilkes-Barre | 0.93 |
| Pennsylvania | 188 | Montrose | 0.90 |
| Pennsylvania | 189 | Doylestown | 1.04 |
| Pennsylvania | 190-191 | Philadelphia | 1.15 |
| Pennsylvania | 193 | Westchester | 1.09 |
| Pennsylvania | 194 | Norristown | 1.08 |
| Pennsylvania | 195-196 | Reading | 0.97 |
| Puerto Rico | 009 | San Juan | 0.74 |
| Rhode Island | 028 | Newport | 1.06 |
| 029 | Providence | 1.07 | |
| South Carolina | 290-292 | Columbia | 0.82 |
| South Carolina | 293 | Spartanburg | 0.81 |
| South Carolina | 294 | Charleston | 0.82 |
| South Carolina | 295 | Florence | 0.76 |
| South Carolina | 296 | Greenville | 0.8 |
| South Carolina | 297 | Rock Hill | 0.72 |
| South Carolina | 298 | Aiken | 0.97 |
| South Carolina | 299 | Beaufort | 0.75 |
| South Dakota | 570-571 | Sioux Falls | 0.76 |
| South Dakota | 572 | Watertown | 0.72 |
| South Dakota | 573 | Mitchell | 0.74 |
| South Dakota | 574 | Aberdeen | 0.75 |
| South Dakota | 575 | Pierre | 0.75 |
| South Dakota | 576 | Mobridge | 0.73 |
| South Dakota | 577 | Rapid City | 0.75 |
| Tennessee | 370-372 | Nashville | 0.85 |
| Tennessee | 373-374 | Chattanooga | 0.77 |
| Tennessee | 375,380-381 | Memphis | 0.83 |
| Tennessee | 376 | Johnson City | 0.72 |
| Tennessee | 377-379 | Knoxville | 0.75 |
| Tennessee | 382 | McKenzie | 0.73 |
| Tennessee | 383 | Jackson | 0.71 |
| Tennessee | 384 | Columbia | 0.73 |
| Tennessee | 385 | Cookeville | 0.72 |
| Texas | 750 | Mckinney | 0.75 |
| Texas | 751 | Wasahackie | 0.75 |
| Texas | 752-753 | Dallas | 0.82 |
| Texas | 754 | Greenville | 0.69 |
| Texas | 755 | Texarkana | 0.73 |
| Texas | 756 | Longview | 0.67 |
| Texas | 757 | Tyler | 0.74 |
| Texas | 758 | Palestine | 0.66 |
| Texas | 759 | Lufkin | 0.71 |
| Texas | 760-761 | Fort Worth | 0.82 |
| Texas | 762 | Denton | 0.77 |
| Texas | 763 | Wichita Falls | 0.79 |
| Texas | 764 | Eastland | 0.73 |
| Texas | 765 | Temple | 0.75 |
| Texas | 766-767 | Waco | 0.78 |
| Texas | 768 | Brownwood | 0.69 |
| Texas | 769 | San Angelo | 0.72 |
| Texas | 770-772 | Houston | 0.86 |
| Texas | 773 | Huntsville | 0.7 |
| Texas | 774 | Wharton | 0.71 |
| Texas | 775 | Galveston | 0.84 |
| Texas | 776-777 | Beaumont | 0.83 |
| Texas | 778 | Bryan | 0.74 |
| Texas | 779 | Victoria | 0.75 |
| Texas | 780 | Laredo | 0.73 |
| Texas | 781-782 | San Antonio | 0.81 |
| Texas | 783-784 | Corpus Christi | 0.78 |
| Texas | 785 | McAllen | 0.76 |
| Texas | 786-787 | Austin | 0.80 |
| Texas | 788 | Del Rio | 0.67 |
| Texas | 789 | Giddings | 0.70 |
| Texas | 790-791 | Amarillo | 0.78 |
| Texas | 792 | Childress | 0.76 |
| Texas | 793-794 | Lubbock | 0.76 |
| Texas | 795-796 | Abilene | 0.75 |
| Texas | 797 | Midland | 0.76 |
| Texas | 798-799,885 | El Paso | 0.75 |
| Utah | 840-841 | Salt Lake City | 0.81 |
| Utah | 842-844 | Ogden | 0.79 |
| Utah | 843 | Logan | 0.80 |
| Utah | 845 | Price | 0.72 |
| Utah | 846-847 | Provo | 0.81 |
| Vermont | 050 | White River Jct | 0.73 |
| Vermont | 051 | Bellows Falls | 0.75 |
| Vermont | 052 | Bennington | 0.82 |
| Vermont | 053 | Brattleboro | 0.78 |
| Vermont | 054 | Burlington | 0.8 |
| Vermont | 056 | Montpelier | 0.81 |
| Vermont | 057 | Rutland | 0.8 |
| Vermont | 058 | St Johnsbury | 0.8 |
| Vermont | 059 | Guildhall | 0.79 |
| Virginia | 220-221 | Fairfax | 1.02 |
| Virginia | 222 | Arlington | 1.04 |
| Virginia | 223 | Alexandria | 1.06 |
| Virginia | 224-225 | Fredericksburg | 0.95 |
| Virginia | 226 | Winchester | 0.93 |
| Virginia | 227 | Culpeper | 1 |
| Virginia | 228 | Harrisonburg | 0.9 |
| Virginia | 229 | Charlottesville | 0.92 |
| Virginia | 230-232 | Richmond | 1.01 |
| Virginia | 233-235 | Norfolk | 1.02 |
| Virginia | 236 | Newport News | 1.01 |
| Virginia | 237 | Portsmouth | 0.92 |
| Virginia | 238 | Petersburg | 0.99 |
| Virginia | 239 | Farmville | 0.91 |
| Virginia | 240-241 | Roanoke | 0.99 |
| Virginia | 242 | Bristol | 0.86 |
| Virginia | 243 | Pulaski | 0.84 |
| Virginia | 244 | Staunton | 0.93 |
| Virginia | 245 | Lynchburg | 0.97 |
| Virginia | 246 | Grundy | 0.85 |
| Washington | 980-981,987 | Seattle | 1.02 |
| Washington | 982 | Everett | 1.05 |
| Washington | 983-984 | Tacoma | 1.01 |
| Washington | 985 | Olympia | 1.01 |
| Washington | 986 | Vancouver | 0.98 |
| Washington | 988 | Wenatchee | 0.93 |
| Washington | 989 | Yakima | 0.97 |
| Washington | 990-992 | Spokane | 0.99 |
| Washington | 993 | Richland | 0.97 |
| Washington | 994 | Clarkston | 0.97 |
| West Virginia | 247-248 | Bluefield | 0.88 |
| West Virginia | 249 | Lewisburg | 0.89 |
| West Virginia | 250-253 | Charleston | 0.97 |
| West Virginia | 254 | Martinsburg | 0.86 |
| West Virginia | 255-257 | Huntington | 1.01 |
| West Virginia | 258-259 | Beckley | 0.90 |
| West Virginia | 260 | Wheeling | 0.93 |
| West Virginia | 261 | Parkersburg | 0.92 |
| West Virginia | 262 | Buckhannon | 0.92 |
| West Virginia | 263-264 | Clarksburg | 0.92 |
| West Virginia | 265 | Morgantown | 0.93 |
| West Virginia | 266 | Gassaway | 0.92 |
| West Virginia | 267 | Romney | 0.88 |
| West Virginia | 268 | Petersburg | 0.90 |
| Wisconsin | 530-532 | Milwaukee | 1.07 |
| Wisconsin | 531 | Kenosha | 1.04 |
| Wisconsin | 534 | Racine | 1.02 |
| Wisconsin | 535 | Beloit | 1.00 |
| Wisconsin | 537 | Madison | 0.99 |
| Wisconsin | 538 | Lancaster | 0.97 |
| Wisconsin | 539 | Portage | 0.96 |
| Wisconsin | 540 | New Richmond | 1.00 |
| Wisconsin | 541-543 | Green Bay | 1.01 |
| Wisconsin | 544 | Wausau | 0.95 |
| Wisconsin | 545 | Rhinelander | 0.95 |
| Wisconsin | 546 | La Crosse | 0.94 |
| Wisconsin | 547 | Eau Claire | 0.98 |
| Wisconsin | 548 | Superior | 0.99 |
| Wisconsin | 549 | Oshkosh | 0.95 |
| Wyoming | 820 | Cheyenne | 0.84 |
| Wyoming | 821 | Yellowstone Nat'l Park | 0.75 |
| Wyoming | 822 | Wheatland | 0.75 |
| Wyoming | 823 | Rawlins | 0.76 |
| Wyoming | 824 | Worland | 0.75 |
| Wyoming | 825 | Riverton | 0.74 |
| Wyoming | 826 | Casper | 0.78 |
| Wyoming | 827 | Newcastle | 0.74 |
| Wyoming | 828 | Sheridan | 0.80 |
| Wyoming | 829-831 | Rock Springs | 0.79 |
Canada: The factors below reflect Canadian currency.
| Province/Territory | City | Factor |
|---|---|---|
| Alberta | Calgary | 1.14 |
|
| Edmonton | 1.13 |
|
| Fort McMurray | 1.09 |
|
| Lethbridge | 1.10 |
|
| Lloydminster | 1.09 |
|
| Medicine Hat | 1.10 |
|
| Red Deer | 1.10 |
| British Columbia | Kamloops | 1.08 |
|
| Prince George | 1.08 |
|
| Vancouver | 1.09 |
|
| Victoria | 1.03 |
| Manitoba | Brandon | 1.06 |
|
| Portage la Prairie | 1.06 |
|
| Winnipeg | 1.05 |
| New Brunswick | Bathurst | 0.97 |
|
| Dalhousie | 0.97 |
|
| Fredericton | 1.05 |
|
| Moncton | 0.98 |
|
| Newcastle | 0.97 |
|
| St John's | 1.05 |
| Newfoundland | Corner Brook | 0.99 |
|
| St John's | 1.01 |
| Northwest Territories | Yellowknife | 1.10 |
| Nova Scotia | Dartmouth | 1.00 |
|
| Halifax | 1.02 |
|
| New Glasgow | 1.00 |
|
| Sydney | 0.99 |
|
| Yarmouth | 1.00 |
| Ontario | Barrie | 1.17 |
|
| Brantford | 1.19 |
|
| Cornwall | 1.19 |
|
| Hamilton | 1.19 |
|
| Kingston | 1.19 |
|
| Kitchener | 1.11 |
|
| London | 1.17 |
|
| North Bay | 1.15 |
|
| Oshawa | 1.17 |
|
| Ottawa | 1.19 |
|
| Owen Sound | 1.15 |
|
| Peterborough | 1.16 |
|
| Sarnia | 1.19 |
|
| Sudbury | 1.09 |
|
| Thunder Bay | 1.15 |
|
| Toronto | 1.20 |
|
| Windsor | 1.14 |
| Prince Edward Island | Charlottetown | 0.95 |
|
| Summerside | 0.94 |
| Quebec | Cap-de-la-Madeleine | 1.18 |
|
| Charlesbourg | 1.18 |
|
| Chicoutimi | 1.20 |
|
| Gatineau | 1.16 |
|
| Laval | 1.17 |
|
| Montreal | 1.21 |
|
| Quebec | 1.22 |
|
| Sherbrooke | 1.17 |
|
| Trois Rivieres | 1.18 |
| Saskatchewan | Moose Jaw | 0.97 |
|
| Prince Albert | 0.96 |
|
| Regina | 0.99 |
|
| Saskatoon | 0.97 |
| Yukon | Whitehours | 0.96 |
Audit Issues and Examination Techniques
Income:Examiners will consider gross income during the examination of all income tax returns. The following techniques are the minimum income probes required for this type of taxpayer. Also consider any large, unusual or questionable income items and if the amount is material, net operating loss deductions. Discuss with Group Manager omitted income items greater than $10,000 and document the discussion on Form 9984. Guidelines for limiting the scope of the examination of income are contained in IRM Section 4.10.4.3.1. Cite the reasons if the scope of the examination of income is limited.
Individual Business Returns: A preliminary Financial Status Analysis based on the tax return and available data will be completed as outlined in IRM 4.10.4.3.3.1(7)(a). If the analysis indicates a material imbalance, the excess expenditures are considered a potential understatement of taxable income and the minimum income probes should be completed. See IRM Section 4.10.4.3.1(2).
Cost of Goods SoldThe following techniques are not intended to be all-inclusive nor are they mandatory steps to be followed. Judgment should be used in selecting the techniques that apply to each taxpayer.
- Check for changes in inventory valuation methods.
- Reconcile beginning and ending inventory with prior and subsequent years.
- Examine cancelled checks, receipts, purchase journals, etc, to validate cost of goods purchased for re-sale and to verify business use of goods.
- Examine cancelled checks, receipts, purchase journals, etc, to validate cost of labor, materials and supplies to raise or produce goods for sale.
- Ensure amount on the return does not include items purchased for personal use.
- Compare cost of labor, materials and supplies to total cost of goods sold for reasonableness.
- Calculate cost of goods sold (Beginning Inventory + Purchases + Labor + Materials + Supplies + Other Costs) - (Withdrawals for Personal Use) - (Ending Inventory).
- Compare calculated Cost of Goods Sold to Cost of Goods Sold on the taxpayer return.
- Reconcile variances.
As of October 31, 2007, EOAD data shows the most frequent issues examined and adjusted on contractor returns (NAICS 238XXX) during FY 2007. If available, use the appropriate examination lead sheets when examining tax issues.
| Issue | % Issues Adjusted |
|---|---|
| Form 1040 Gross Receipts or Sales | 63.37% |
| Form 1040 Cost of Goods Sold | 65.48% |
| Form 1040 Depreciation and Sec 179 Expense Deduction | 71.31% |
| Form 1040 Car and Truck Expenses | 74.02% |
| Form 1040 Supplies | 75.28% |
| Form 1040 Repairs and Maintenance | 76.27% |
| Form 1040 Insurance (Other than Health) | 78.43% |
| Form 1040 Other Expenses | 78.49% |
| Form 1040 | 80.64% |
| Form 1040 Meals and Entertainment | 85.80% |
| Form 1065 Purchases | 51.28% |
| Form 1065 Gross Receipts or Sales | 52.69% |
| Form 1065 Other Costs | 54.76% |
| Form 1065 Cost of Goods Sold (No Schedule A) | 57.14% |
| Form 1065 Guaranteed Payments to Partners | 57.89% |
| Form 1065 Cost of Labor | 60.00% |
| Form 1065 Other Expenses | 73.08% |
| Form 1065 Taxes & Licenses | 84.21% |
| Form 1065 Sec 179 Expense Deduction | 85.71% |
| Form 1065 Other Deductions (No Schedule) | 86.21% |
| Form 1065 Ordinary Income (loss) | 94.74% |
| Form 1065 Gross Nonfarm Income | 95.24% |
| Form 1065 Depreciation | 100.00% |
| Form 1120 Other Costs | 30.05% |
| Form 1120 Gross Receipts or Sales | 33.45% |
| Form 1120 Purchases | 35.34% |
| Form 1120 Cost of Goods Sold (No Schedule A) | 37.00% |
| Form 1120 Compensation of Officers | 47.58% |
| Form 1120 Auto & Truck Expenses | 55.47% |
| Form 1120 Other Deductions | 60.38% |
| Form 1120 Depreciation | 65.14% |
| Form 1120 Other Expenses | 67.39% |
| Form 1120 Net Operating Loss Deduction | 86.57% |
| Form 1120S Cost of Labor | 29.69% |
| Form 1120S Other Costs | 38.85% |
| Form 1120S Insurance Expense | 44.74% |
| Form 1120S Purchases | 47.06% |
| Form 1120S Gross Receipts or Sales | 47.48% |
| Form 1120S Compensation of Officers | 50.87% |
| Form 1120S Total Property Distributions | 53.41% |
| Form 1120S Automobile Expense | 64.29% |
| Form 1120S Other Expenses | 70.86% |
| Form 1120S Depreciation | 73.01% |
Other:
Related Returns: Determine whether the related return warrants examination from a classification perspective. For example, trace transactions between the related taxpayers, complete a financial status analysis based on the return and internal sources of information and review the return for other potential issues. See IRM Section 4.10.5.4.
Net Operating Loss Deduction: The following techniques are not intended to be all-inclusive nor are they mandatory steps to be followed. Judgment should be used in selecting the techniques that apply to each taxpayer.
- Review or prepare a schedule of the net operating loss deductions and how they were carried back or over.
- Determine if a timely irrevocable election under IRC § 172(b)(3) to relinquish the entire carryback period was made. IRC § 172(b)(1)(A) generally allows an NOL to be carried back 2 years and carried forward 20 years for tax years beginning after August 5, 1997. For tax years beginning on or before August 5, 1997, carrybacks were generally allowed three years back and fifteen years forward. A five-year carryback period was allowed for NOL's arising in a tax year ending during 2001 or 2002.The election has to be made on a timely filed return, including extension. In addition, in the instruction to the Form 1139, the IRS has stated that the election to forego the carryback can be made on an amended return filed within 6 months of the due date (including extensions) of the loss year. Special rules may apply to farming losses.
- Determine if the NOL was properly carried back. It must be carried back first to any preceding years prior to any carryforward.
- Determine the correct NOLD in the year under examination. Generally, this does not require the NOL year(s) to be put under examination though you are allowed to review any NOL year or carryover year in order to determine the correct NOLD in the year under examination. If the carryover NOLD includes nondeductible penalties (determined by examining the transcript for transaction codes - 160s, 170s or 180s), reduce the carryover by the penalty amounts.
- When making current year adjustments, evaluate whether the issue existed in a prior year, it may result in reduction in the current NOLD carryforward.
- Determine if the NOLD applied in consolidated returns and carried over from acquired entities meets the limitations of IRC sections 381 and 382 and the SRLY rules found in the regulations under IRC section 1502.
- Compare computations for the regular NOL and the alternative minimum tax.
- Flag the return with NOL carrybacks to indicate that restricted interest is involved.
- Determine if the contribution deduction was treated properly. There is no contribution deduction allowable in the NOL year or any carryforward year where taxable income is completely eliminated. Note: There are not changes for carryback years for contributions. IR.C § 172(d)(5).